Search Documents
No Results Found.
No Results Found.
Solicitation Amendment W911SG26BA0090001 SF 30.pdf
Posted: Aug. 14, 2026
• Type: .pdf
• Size: 4.05MB
Submit Questions to Government Officer Anonymously
Place your question(s) below. One of our analysts will anonymously submit the question(s) within 8 hours and provide any responses via email once received.
Opportunity Assistant
Hello! Please let me know your questions about this document.
Loading
Save a Question
Customize Generation
We will write a draft based on the below linked information. Add or link more information to improve the draft.
Federal Profile
Select the Federal company profile to use when informing the response based on publicly available data.
Loading federal profile search...
Company Context
Add capability statements, prior responses, or other company materials to customize the response to your business.
Checking for company documents...
Opportunity Context
Add SOWs, attachments, or other files specific to this opportunity.
Checking for opportunity documents...
Link a Pursuit
Optionally associate this draft with an existing pursuit.
Overview
Related Opportunity
Related Agency
Profiled People
Summary
This **Solicitation Amendment** issued under solicitation **W911SG26BA0090001** updates the Fort Bliss requirement to replace six Carrier rooftop HVAC units at Building 1611 under project work order **FE 10216 5J**, with performance required within **270 calendar days after contract award**.
The amended scope requires replacement units to be Trane units or approved equals of the same capacity. Demolition is limited to Carrier units **A8, A10, A11, A12, A14, and A15**, and may occur only after submittals are approved and replacement equipment is on site.
Work will occur in the occupied Post Exchange and must maintain heating and cooling through an approved phasing plan, temporary systems as needed, and coordination with the COR and tenant.
The amendment establishes extensive submittal and preconstruction requirements, including submission of the following within 14 days of award and completion within 60 days:
- Site-Specific Safety Plan
- AHA
- QCP
- SWPPP
- SCLMR dig permit
- TCP
The contractor must begin project performance no later than 90 days after award. Delays in completing the SCLMR without timely written justification may result in liquidated damages calculated at **$1,717.24 per calendar day**.
Mobilization and construction cannot begin until the Government conducts a preconstruction meeting. The contractor must obtain all required permits, licenses, bonds, insurance, and approvals.
The technical requirements include high-efficiency, LEED-compliant RTUs with the following features:
- Factory-installed hail guards
- Economizers with comparative enthalpy control
- Barometric relief
- MERV-13 filters
- Phase-loss protection
- Stainless-steel heat exchangers
- 14-inch factory-fabricated adapt-a-curbs
- Programmable LCD temperature sensors with override buttons
- CO₂ sensors
- Natural-gas altitude kits
- Powered convenience outlets
The contractor must provide or modify ductwork, insulation, condensate drains, breakers, disconnects, wiring, labeling, smoke detectors, and controls. The contractor must also recover and document R-410A refrigerant; protect and label existing LonWorks control wiring without performing basewide integration; and obtain independent NEBB-certified-or-equal testing and balancing reports.
Additional requirements address fire protection and hot-work permits, occupied-facility coordination, waste disposal, crane notification at least two weeks in advance, utility outages, fire-alarm testing with Fort Bliss authorities, project signage, and strict compliance with applicable federal, state, local, NFPA, NEC, IMC, SMACNA, ASHRAE, manufacturer, and contract requirements.
The amended scope requires replacement units to be Trane units or approved equals of the same capacity. Demolition is limited to Carrier units **A8, A10, A11, A12, A14, and A15**, and may occur only after submittals are approved and replacement equipment is on site.
Work will occur in the occupied Post Exchange and must maintain heating and cooling through an approved phasing plan, temporary systems as needed, and coordination with the COR and tenant.
The amendment establishes extensive submittal and preconstruction requirements, including submission of the following within 14 days of award and completion within 60 days:
- Site-Specific Safety Plan
- AHA
- QCP
- SWPPP
- SCLMR dig permit
- TCP
The contractor must begin project performance no later than 90 days after award. Delays in completing the SCLMR without timely written justification may result in liquidated damages calculated at **$1,717.24 per calendar day**.
Mobilization and construction cannot begin until the Government conducts a preconstruction meeting. The contractor must obtain all required permits, licenses, bonds, insurance, and approvals.
The technical requirements include high-efficiency, LEED-compliant RTUs with the following features:
- Factory-installed hail guards
- Economizers with comparative enthalpy control
- Barometric relief
- MERV-13 filters
- Phase-loss protection
- Stainless-steel heat exchangers
- 14-inch factory-fabricated adapt-a-curbs
- Programmable LCD temperature sensors with override buttons
- CO₂ sensors
- Natural-gas altitude kits
- Powered convenience outlets
The contractor must provide or modify ductwork, insulation, condensate drains, breakers, disconnects, wiring, labeling, smoke detectors, and controls. The contractor must also recover and document R-410A refrigerant; protect and label existing LonWorks control wiring without performing basewide integration; and obtain independent NEBB-certified-or-equal testing and balancing reports.
Additional requirements address fire protection and hot-work permits, occupied-facility coordination, waste disposal, crane notification at least two weeks in advance, utility outages, fire-alarm testing with Fort Bliss authorities, project signage, and strict compliance with applicable federal, state, local, NFPA, NEC, IMC, SMACNA, ASHRAE, manufacturer, and contract requirements.
Show All