P1062 design-bid-build, dry dock 3 modernization, norfolk naval shipyard, portsmouth VA. The project involves rebuilding caisson seats with deep foundations, refurbishing the dock floor and walls, pinning the concrete floor, constructing a wet well and pump house to replace the existing pumpwell, rerouting utilities into a new utility trench around the dock perimeter, and replacing the dry dock’s surrounding rail systems. Additional work includes constructing a temporary cofferdam at the entrance, reconstructing the floors and walls with reinforced concrete to accommodate increased load conditions, and selective demolition of the existing below grade pumpwell to facilitate new discharge piping. The modernization supports updated submarine dry dock requirements and removes operational restrictions for docking submarines.
Place of Performance
Portsmouth, VA 23709 United States
Pricing
Fixed Price With Economic Price Adjustment
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
MEB General Contractors was awarded Definitive Contract N6247026C0001 (N62470-26-C-0001) for Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth VA worth up to $467,181,292 by Naval Facilities Engineering Command in December 2025. The contract has a duration of 5 years 1 months and was awarded through solicitation MILITARY CONSTRUCTION PROJECT (MILCON) P1062 DESIGN-BID-BUILD, DRY DOCK 3 MODERNIZATION, NORFOLK NAVAL SHIPYARD, PORTSMOUTH, VIRGINIA full & open with NAICS 237990 and PSC Y1ED via direct negotiation acquisition procedures with 3 bids received. As of today, the Definitive Contract has a total reported backlog of $300,003,792 and funded backlog of $274,949,500.

DOD Announcements

Dec 2025: MEB General Contractors Inc., Chesapeake, Virginia, is awarded a $442,127,000 firm-fixed-price, award-fee-incentive with economic-price-adjustment contract for modernization of Dry Dock #3 at Norfolk Naval Shipyard. Work will be performed at Portsmouth, Virginia, and is expected to be completed by January 2031. The maximum dollar value, including unexercised options and potential award fee, is $467,181,292. The contract will be incrementally funded with fiscal 2025 and future fiscal year military construction (Navy) funds. Fiscal 2025 funds in the amount of $42,177,500, will be obligated at time of award. This contract was competitively procured via the System for Award Management website, with three offers received. The Naval Facilities Engineering Systems Command, Atlantic, Norfolk, Virginia, is the contracting activity (N62470-26-C-0001).

Status
(Open)

Last Modified 1/8/26
Period of Performance
12/4/25
Start Date
1/10/31
Current End Date
1/10/31
Potential End Date
7.0% Complete

Obligations and Backlog
$167.2M
Total Obligated
$442.1M
Current Award
$467.2M
Potential Award
36% Funded
$274.9M
Funded Backlog
$300.0M
Total Backlog

Award Hierarchy

Definitive Contract

N6247026C0001

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to N6247026C0001

Opportunity Lifecycle

Procurement history for N6247026C0001

Transaction History

Modifications to N6247026C0001

People

Suggested agency contacts for N6247026C0001

Competition

Number of Bidders
3
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
EJHTLA7NAFH4
Awardee CAGE
0CVN7
Agency Detail
Awarding Office
N62470 NAVFACSYSCOM ATLANTIC
Funding Office
N62470
Created By
edward.d.flint.civ.n62470@us.navy.mil
Last Modified By
edward.d.flint.civ.n62470@us.navy.mil
Approved By
edward.d.flint.civ.n62470@us.navy.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
VA-03
Senators
Mark Warner
Timothy Kaine
Representative
Robert Scott
Modified: 1/8/26