Engineered drawings with Hydraulic calculation will be submitted to the Fire Prevention Office for review. Tie-in point for the work is a flanged spigot piece located appproximately 1'0" A.F.F. Install detector check backflow preventer with OS & Y valves with tamper switches, riser check valve assembly, ifre department connection with Knox Caps and backflow bypass. FDC and Backflor Preventer test opening to be installed on the exterior wall at the riser location. Install new mains and branch lines to supply chrome pendant and brass upright sprinkler heads on concealed and exposed piping. Use earthquake bracing installation. Core drilling of masonry wall, if required.
Sub Awardee
Total Awarded
$32,233.18
Most Recent Award Date
Oct. 8, 2013
Place of Performance
Ft. Knox, Kentucky 40121-0908 United States
Prime Awardee
Prime Project Title
Bldg. 6014 Renovations
Prime Award
Award Hierarchy
Related Subcontracts
Subcontracts under the same prime contract
Subcontract History
Disclosed subcontract actions
Prime Contract Details
Prime Status
Period of Performance
9/17/13
Start Date
3/31/14
Current End Date
3/31/14
Potential End Date
Obligations
$710.0K
Total Obligated
$710.0K
Current Value
$710.0K
Potential Value
Prime Overview
Original Description
RENOVATION BUILDING 6014.
Awarding / Funding Agency
NAICS
Not Reported
Pricing
Fixed Price
Place of Performance
Fort Knox, KY 40121 United States
Set Aside
None
Extent Competed
Full And Open Competition