Description
Background
The Holleman Substation Construction project is initiated by Bryan Texas Utilities (BTU) to enhance the electrical infrastructure in the region. The goal is to construct a new 138kV substation that will interject into the existing South Switch to Dowling Road 138kV transmission line. This project aims to improve reliability and capacity for electricity distribution in College Station, Texas.
Work Details
The scope of work includes:
- Construction of a new 138kV Holleman Substation, which will consist of a ring bus with two-line terminals, two terminals for power transformers, and a terminal for three capacitor banks.
- Installation of all necessary equipment including power transformers and capacitor banks, with some equipment provided by BTU requiring relocation by the contractor.
- Roadway improvements along Old Wellborn Road to facilitate access to the site.
- Specific tasks include clearing, grading, erosion control, installation of underground detention systems, landscaping, and construction of concrete walls and fencing.
- Installation of various components such as ground grids, foundations, substation steel, bus work, breakers, switches, control houses, lighting systems, relay panels, and HVAC systems.
- The contractor must also manage permitting and inspections required by College Station authorities.
Period of Performance
The anticipated construction commencement is scheduled for September 2026 with completion expected by December 2027.
Place of Performance
The primary location for this contract is at the Holleman Substation site located at 11720 Old Wellborn Road, College Station, TX 77845. Additional work may occur at remote ends including Dowling Road Substation and South Switch Switchyard.
Bidder Requirements
Bidders must attend a mandatory pre-bid meeting and site visit on June 29, 2026. They are required to submit a bid bond of at least five percent (5%) of the total bid amount along with their proposal. Bidders must also provide resumes of personnel committed to the project and complete various forms including a Bid Unit Proposal Form and Certification of Bid.
The Holleman Substation Construction project is initiated by Bryan Texas Utilities (BTU) to enhance the electrical infrastructure in the region. The goal is to construct a new 138kV substation that will interject into the existing South Switch to Dowling Road 138kV transmission line. This project aims to improve reliability and capacity for electricity distribution in College Station, Texas.
Work Details
The scope of work includes:
- Construction of a new 138kV Holleman Substation, which will consist of a ring bus with two-line terminals, two terminals for power transformers, and a terminal for three capacitor banks.
- Installation of all necessary equipment including power transformers and capacitor banks, with some equipment provided by BTU requiring relocation by the contractor.
- Roadway improvements along Old Wellborn Road to facilitate access to the site.
- Specific tasks include clearing, grading, erosion control, installation of underground detention systems, landscaping, and construction of concrete walls and fencing.
- Installation of various components such as ground grids, foundations, substation steel, bus work, breakers, switches, control houses, lighting systems, relay panels, and HVAC systems.
- The contractor must also manage permitting and inspections required by College Station authorities.
Period of Performance
The anticipated construction commencement is scheduled for September 2026 with completion expected by December 2027.
Place of Performance
The primary location for this contract is at the Holleman Substation site located at 11720 Old Wellborn Road, College Station, TX 77845. Additional work may occur at remote ends including Dowling Road Substation and South Switch Switchyard.
Bidder Requirements
Bidders must attend a mandatory pre-bid meeting and site visit on June 29, 2026. They are required to submit a bid bond of at least five percent (5%) of the total bid amount along with their proposal. Bidders must also provide resumes of personnel committed to the project and complete various forms including a Bid Unit Proposal Form and Certification of Bid.
Loading Map
Loading Map
Overview
Agency
Opportunity Type
BTU - Request for Bid - Electronic
Opportunity ID
032-09-26
Response Deadline
July 29, 2026
Due in 35 Days
Date Posted
June 17, 2026
Source
Pre-Bid Conference
Mandatory pre-bid meeting and site visit. Site visit immediately following the pre-bid meeting. Bidders must attend on June 29, 2026.
Est. Value Range
Experimental
$12,000,000 - $28,000,000
(AI estimate)
Agency Distribution
High
On 6/17/26 Brazos Valley in Texas issued BTU - Request for Bid - Electronic Holleman Substation Construction with ID 032-09-26 due 7/29/26.
Contacts
Documents
Posted documents for Holleman Substation Construction
Opportunity Assistant
AI Analysis
AI Generate