Tiftonia Pump Station #2 Improvements
ID: 200769 • State: Tennessee
Opportunity Assistant
Loading
Description
Background
The City of Chattanooga, Tennessee, is issuing a solicitation for the Tiftonia Pump Station #2 Improvements project. The goal of this contract is to enhance the sewage pumping infrastructure to ensure efficient and reliable wastewater management in the area.
Work Details
The project involves the demolition of an existing sewage pumping station, electrical equipment, fencing, and other site appurtenances.
The construction of a new submersible pumping station will include:
- Three new pumps
- A valve vault
- A flowmeter
- A bypass pump connection
- Electrical control and power cabinets with shelter
- Concrete pads
- 47 linear feet of 24-inch gravity sewer main
- Two 6-foot diameter manholes
- Bypass pumping
- Site grading
- Drainage work
- Stone and asphalt paving
Additional necessary appurtenances will be included for a complete and functional installation.
Period of Performance
The contract is expected to be completed within 240 calendar days from the notice to proceed.
Place of Performance
The work will be performed in Chattanooga, Tennessee.
The City of Chattanooga, Tennessee, is issuing a solicitation for the Tiftonia Pump Station #2 Improvements project. The goal of this contract is to enhance the sewage pumping infrastructure to ensure efficient and reliable wastewater management in the area.
Work Details
The project involves the demolition of an existing sewage pumping station, electrical equipment, fencing, and other site appurtenances.
The construction of a new submersible pumping station will include:
- Three new pumps
- A valve vault
- A flowmeter
- A bypass pump connection
- Electrical control and power cabinets with shelter
- Concrete pads
- 47 linear feet of 24-inch gravity sewer main
- Two 6-foot diameter manholes
- Bypass pumping
- Site grading
- Drainage work
- Stone and asphalt paving
Additional necessary appurtenances will be included for a complete and functional installation.
Period of Performance
The contract is expected to be completed within 240 calendar days from the notice to proceed.
Place of Performance
The work will be performed in Chattanooga, Tennessee.
Loading Map
Loading Map
Overview
Agency
Opportunity Type
Construction Bid
Opportunity ID
200769
Response Deadline
April 24, 2025
Past Due
Date Posted
March 16, 2025
Est. Value Range
Experimental
$2,000,000 - $5,000,000
(AI estimate)
Agency Distribution
Moderate
Source
On 3/16/25 City of Chattanooga in Tennessee issued Construction Bid Tiftonia Pump Station #2 Improvements with ID 200769 due 4/24/25.
Contacts
Documents
Posted documents for Tiftonia Pump Station #2 Improvements
Opportunity Assistant
AI Analysis
AI Generate