Background
The Town of Fort Mill, South Carolina is seeking competitive bids for the 2025 Road Paving Project. The purpose of this project is to address various paving needs within the town, ensuring safe and accessible roadways for residents and visitors.
The project aims to enhance the infrastructure of Fort Mill as part of its ongoing commitment to community development.
Work Details
The scope of work includes:
1. Looms Way:
- Cut and remove damaged curbing (10 LF). If the dirt base is soft, remove subgrade until a solid foundation is found. Fill and compact with rock.
- Total Asphalt Replacement: Remove existing asphalt pavement to a depth of 10” (980 SY), provide and compact a 6” aggregate base course, pave with 2” intermediate course asphalt and 2” surface course asphalt (980 SY).
2. Calhoun Street:
- Cut and remove damaged curbing (45 LF). If the dirt base is soft, remove subgrade until a solid foundation is found. Fill and compact with rock.
- Total Asphalt Replacement: Remove existing asphalt pavement to a depth of 10” (1172 SY), provide and compact a 6” aggregate base course, pave with 2” intermediate course asphalt and 2” surface course asphalt (1172 SY).
- Sidewalk Repair: Cut and remove damaged sidewalk (4256 SF), haul off debris, pour removed areas, backfill around sidewalk.
3. Phillips Street:
- Total reconstruction: Remove existing asphalt pavement (895 SY) to a depth of 10”, provide and compact a 6” aggregate base course, pave with 2” intermediate course asphalt and 2” surface course asphalt for (895 SY).
4. Monroe White Street:
- Cut and remove damaged curbing; if the dirt base is soft, remove subgrade until a solid foundation is found. Fill and compact with rock. Pour back to existing curbing.
- Total Asphalt Replacement: Remove existing asphalt pavement totaling 2524 SY to a depth of 10”, provide and compact a 6” aggregate base course over 2524 SY, pave with 2” intermediate course asphalt and 2” surface course asphalt over 2524 SY.
- Sidewalk Repair: Remove approx. 5445 SF of existing concrete walkway; haul off debris; pour back approximately 5445 SF with new concrete (4”).
5. Pine Knoll Road:
- Provide traffic control for residents; milling at a depth of 6” on entire surface (2582 SY); roll subgrade; perform asphalt paving including a 3” base course Type B/C (2582 SY), a 2” intermediate course using SCDOT mix only (2582 SY), and a final surface course of 1.5” using SCDOT mix only (2582 SY). Clean up grade/ensure crown.
Period of Performance
The contract will be performed from the date of award until completion, anticipated by August 13, 2025.
Place of Performance
The work will be performed in various locations throughout the Town of Fort Mill, South Carolina.
Bidder Requirements
Bidders must possess or obtain a Town of Fort Mill Business License prior to execution of the contract. They must maintain all required licenses, permits, liability insurance ($1 million per occurrence), worker’s compensation insurance, and comply with all federal, state, county or Town statutes during performance.
The Town of Fort Mill, South Carolina is seeking competitive bids for the 2025 Road Paving Project. The purpose of this project is to address various paving needs within the town, ensuring safe and accessible roadways for residents and visitors.
The project aims to enhance the infrastructure of Fort Mill as part of its ongoing commitment to community development.
Work Details
The scope of work includes:
1. Looms Way:
- Cut and remove damaged curbing (10 LF). If the dirt base is soft, remove subgrade until a solid foundation is found. Fill and compact with rock.
- Total Asphalt Replacement: Remove existing asphalt pavement to a depth of 10” (980 SY), provide and compact a 6” aggregate base course, pave with 2” intermediate course asphalt and 2” surface course asphalt (980 SY).
2. Calhoun Street:
- Cut and remove damaged curbing (45 LF). If the dirt base is soft, remove subgrade until a solid foundation is found. Fill and compact with rock.
- Total Asphalt Replacement: Remove existing asphalt pavement to a depth of 10” (1172 SY), provide and compact a 6” aggregate base course, pave with 2” intermediate course asphalt and 2” surface course asphalt (1172 SY).
- Sidewalk Repair: Cut and remove damaged sidewalk (4256 SF), haul off debris, pour removed areas, backfill around sidewalk.
3. Phillips Street:
- Total reconstruction: Remove existing asphalt pavement (895 SY) to a depth of 10”, provide and compact a 6” aggregate base course, pave with 2” intermediate course asphalt and 2” surface course asphalt for (895 SY).
4. Monroe White Street:
- Cut and remove damaged curbing; if the dirt base is soft, remove subgrade until a solid foundation is found. Fill and compact with rock. Pour back to existing curbing.
- Total Asphalt Replacement: Remove existing asphalt pavement totaling 2524 SY to a depth of 10”, provide and compact a 6” aggregate base course over 2524 SY, pave with 2” intermediate course asphalt and 2” surface course asphalt over 2524 SY.
- Sidewalk Repair: Remove approx. 5445 SF of existing concrete walkway; haul off debris; pour back approximately 5445 SF with new concrete (4”).
5. Pine Knoll Road:
- Provide traffic control for residents; milling at a depth of 6” on entire surface (2582 SY); roll subgrade; perform asphalt paving including a 3” base course Type B/C (2582 SY), a 2” intermediate course using SCDOT mix only (2582 SY), and a final surface course of 1.5” using SCDOT mix only (2582 SY). Clean up grade/ensure crown.
Period of Performance
The contract will be performed from the date of award until completion, anticipated by August 13, 2025.
Place of Performance
The work will be performed in various locations throughout the Town of Fort Mill, South Carolina.
Bidder Requirements
Bidders must possess or obtain a Town of Fort Mill Business License prior to execution of the contract. They must maintain all required licenses, permits, liability insurance ($1 million per occurrence), worker’s compensation insurance, and comply with all federal, state, county or Town statutes during performance.
Overview
Agency
Opportunity ID
RFP 500-140
Response Deadline
Aug. 13, 2025
Past Due
Date Posted
July 24, 2025
Source
Pre-Bid Conference
no pre bid meeting
Est. Value Range
Experimental
$500,000 - $1,500,000
(AI estimate)
Agency Distribution
Low
On 7/24/25 Town of Fort Mill in South Carolina issued 2025 Town of Fort Mill Road Paving Project with ID RFP 500-140 due 8/13/25.
Contacts
Documents
Posted documents for 2025 Town of Fort Mill Road Paving Project RFP 500-140
Opportunity Assistant
AI Analysis
AI Generate
Classifications
Opportunity Classification
RFP 500-140