Background
The Durham WRRF Odor Control Phase 3 Headworks Project No. 7202 is being issued by Clean Water Services, located in Tigard, Oregon. The project aims to enhance odor control at the Durham Water Resource Recovery Facility. This public works project is subject to Oregon Revised Statutes (ORS) 279C.800 to 279C.870 and has an estimated construction cost of $4,240,000.
Work Details
The work includes the following tasks:
1. Construct and commission a new engineered media biofilter, which will be a single-cell reinforced concrete basin with integral air distribution, internal high-density polyethylene liner, engineered media, media floor support system, water panel, and humidification and irrigation system.
2. Install and commission two new odor control fans adjacent to the biofilter.
3. Modify, re-route, and provide new foul air ducting and supports within the Headworks facility to connect to the new odor control fans and biofilter.
4. Demolish the existing odor mist scrubber including the existing odor exhaust fan, unused foul air duct, low-pressure air piping, and chemical piping.
5. Install and commission two Owner-furnished variable speed drives in the upper electrical room.
6. Install instrumentation and control stations along with associated conduits, conductors, and other necessary appurtenances for completion of the work.
7. Fill abandoned force mains within the footprint of the new biofilter with grout as indicated in the drawings.
8. Finish grading to integrate the biofilter into the earthen bank south of Headworks including a new concrete stairway alongside the north edge of the biofilter and a cart path extending south from the fan pad to the digester gas treatment skid.
9. Install site lighting for access around the biofilter, odor control fans, and cart path.
10. Install irrigation sleeves at hardscape crossings; final landscaping will be managed by Owner.
11. Install new drainage piping and manhole for connecting the biofilter drain to the existing sanitary sewer line.
Period of Performance
The contract work is expected to commence upon award and must be completed by April 9, 2026.
Place of Performance
The work will be performed at Durham Water Resource Recovery Facility located at 16580 SW 85th Avenue, Tigard, Oregon 97224.
Bidder Requirements
Bidders must be registered with the Oregon Construction Contractors Board prior to submitting a bid for this public works project. They are required to submit a First-Tier Subcontractor Disclosure Form identifying subcontractors that will furnish labor or materials equal to at least five percent of the contract price or $15,000 (whichever is greater). Bidders must also comply with prevailing wage laws as per ORS 279C.
The Durham WRRF Odor Control Phase 3 Headworks Project No. 7202 is being issued by Clean Water Services, located in Tigard, Oregon. The project aims to enhance odor control at the Durham Water Resource Recovery Facility. This public works project is subject to Oregon Revised Statutes (ORS) 279C.800 to 279C.870 and has an estimated construction cost of $4,240,000.
Work Details
The work includes the following tasks:
1. Construct and commission a new engineered media biofilter, which will be a single-cell reinforced concrete basin with integral air distribution, internal high-density polyethylene liner, engineered media, media floor support system, water panel, and humidification and irrigation system.
2. Install and commission two new odor control fans adjacent to the biofilter.
3. Modify, re-route, and provide new foul air ducting and supports within the Headworks facility to connect to the new odor control fans and biofilter.
4. Demolish the existing odor mist scrubber including the existing odor exhaust fan, unused foul air duct, low-pressure air piping, and chemical piping.
5. Install and commission two Owner-furnished variable speed drives in the upper electrical room.
6. Install instrumentation and control stations along with associated conduits, conductors, and other necessary appurtenances for completion of the work.
7. Fill abandoned force mains within the footprint of the new biofilter with grout as indicated in the drawings.
8. Finish grading to integrate the biofilter into the earthen bank south of Headworks including a new concrete stairway alongside the north edge of the biofilter and a cart path extending south from the fan pad to the digester gas treatment skid.
9. Install site lighting for access around the biofilter, odor control fans, and cart path.
10. Install irrigation sleeves at hardscape crossings; final landscaping will be managed by Owner.
11. Install new drainage piping and manhole for connecting the biofilter drain to the existing sanitary sewer line.
Period of Performance
The contract work is expected to commence upon award and must be completed by April 9, 2026.
Place of Performance
The work will be performed at Durham Water Resource Recovery Facility located at 16580 SW 85th Avenue, Tigard, Oregon 97224.
Bidder Requirements
Bidders must be registered with the Oregon Construction Contractors Board prior to submitting a bid for this public works project. They are required to submit a First-Tier Subcontractor Disclosure Form identifying subcontractors that will furnish labor or materials equal to at least five percent of the contract price or $15,000 (whichever is greater). Bidders must also comply with prevailing wage laws as per ORS 279C.
Loading Map
Loading Map
Overview
Agency
Opportunity ID
7202
Response Deadline
April 9, 2026
Past Due
Date Posted
March 9, 2026
Source
Est. Value Range
Experimental
$4,240,000
(Agency Estimate)
On 3/9/26 Clean Water Services in Oregon issued Durham WRRF Odor Control Phase 3 Headworks Project with ID 7202 due 4/8/26.
Contacts
Documents
Posted documents for ITB - Durham WRRF Odor Control Phase 3 Headworks Project No. 7202
Opportunity Assistant
AI Analysis
AI Generate