L1407-C1, Rehabilitate Terminal B/C, C, And C/E Alleyways, Logan International Airport, East Boston,
ID: BD-19-1411-CAPPR-LOC1-126694
• State: Massachusetts
Opportunity Assistant
Loading
Description
Background
The Massachusetts Port Authority is issuing this contract for the rehabilitation of Terminal B/C, C, and C/E alleyways at Logan International Airport in East Boston, Massachusetts. The goal of this contract is to enhance the infrastructure of the airport to ensure safety and efficiency in operations.
Work Details
The contractor will be responsible for the following services:
- Pavement milling
- Crack sealing and crack repair
- Utility structure adjustments
- Hot mix asphalt paving
- Portland cement concrete hard stands
- Pavement markings
The estimated contract cost is $7,600,000.
Period of Performance
The contract work is expected to commence after the bid opening on April 8, 2026, with specific timelines to be determined based on the awarded proposal.
Place of Performance
Logan International Airport, East Boston, Massachusetts.
Bidder Requirements
Bidders must submit a Buy American Certificate with all bids or offers on AIP funded projects. A proposal guaranty consisting of a bid deposit for five percent of the value of the bid is required. The successful bidder must furnish a performance bond and a labor and materials payment bond equal to 100% of the contract price. Additionally, contractors with fifty or more employees must develop a written affirmative action compliance program within 120 days from contract commencement.
The Massachusetts Port Authority is issuing this contract for the rehabilitation of Terminal B/C, C, and C/E alleyways at Logan International Airport in East Boston, Massachusetts. The goal of this contract is to enhance the infrastructure of the airport to ensure safety and efficiency in operations.
Work Details
The contractor will be responsible for the following services:
- Pavement milling
- Crack sealing and crack repair
- Utility structure adjustments
- Hot mix asphalt paving
- Portland cement concrete hard stands
- Pavement markings
The estimated contract cost is $7,600,000.
Period of Performance
The contract work is expected to commence after the bid opening on April 8, 2026, with specific timelines to be determined based on the awarded proposal.
Place of Performance
Logan International Airport, East Boston, Massachusetts.
Bidder Requirements
Bidders must submit a Buy American Certificate with all bids or offers on AIP funded projects. A proposal guaranty consisting of a bid deposit for five percent of the value of the bid is required. The successful bidder must furnish a performance bond and a labor and materials payment bond equal to 100% of the contract price. Additionally, contractors with fifty or more employees must develop a written affirmative action compliance program within 120 days from contract commencement.
Loading Map
Loading Map
Overview
Opportunity Type
Open Market
Opportunity ID
BD-19-1411-CAPPR-LOC1-126694
Response Deadline
April 8, 2026
Past Due
Date Posted
March 18, 2026
Source
Pre-Bid Conference
9:00 AM LOCAL TIME ON WEDNESDAY, MARCH 25, 2026. THE FOLLOWING VIRTUAL INSTRUCTIONS SHALL BE USED BY ALL PARTICIPANTS: https://teams.microsoft.com/meet/21691174390602?p=udDPhoPJWegjyxzUWk
Est. Value Range
Experimental
$7,000,000 - $8,000,000
(AI estimate)
Agency Distribution
High
On 3/18/26 Massachusetts Port Authority (Massport) in Massachusetts issued Open Market Rehabilitate Terminal B/C, C, And C/E Alleyways, Logan International Airport, East Boston with ID BD-19-1411-CAPPR-LOC1-126694 due 4/8/26.
Contacts
Documents
Posted documents for L1407-C1, Rehabilitate Terminal B/C, C, And C/E Alleyways, Logan International Airport, East Boston,
Opportunity Assistant
AI Analysis
AI Generate
Classifications
NAICS
UNSPSC
721000 - Building construction and support and maintenance and repair
Additional Details
Source Department
CAPPROG - Capital Programs
Source Location
LOC1 - Logan Office Center 1
Info Contact
Luciana Burdi