Description
Background
The Auraria Road at Burnt Stand Road Roundabout project is initiated by the Lumpkin County Board of Commissioners. The project aims to enhance traffic flow and safety by constructing a four-leg roundabout at the intersection of Auraria Road and Burnt Stand Road, which also includes access to The White Oak Learning Academy.
This initiative is part of the county's commitment to improving local infrastructure using local funds while adhering to state and local construction laws.
Work Details
The work involves furnishing and installing all necessary materials, labor, tools, equipment, and related services for a complete project. Key components include:
- Construction of a complete four-leg roundabout intersection at Auraria Rd. and Burnt Stand Rd.
- Entrance road construction into The White Oak Learning Academy.
- Approximately 2,900 linear feet (L.F.) of roadway including:
- Asphalt pavement
- Concrete curb and gutter
- Concrete truck apron
- Sidewalks
- Driveway replacements
- Crosswalks
- Raised medians
- Signage and markings
- Storm drainage structures and piping
- Site grading, sodding, and erosion control in accordance with Contract Documents.
Period of Performance
The specific period of performance is not detailed in the provided solicitation text; however, it indicates that the work must be completed within a timeframe set forth in the Bid Form and Form of Agreement.
Place of Performance
The contract will be performed at the intersection of Auraria Road and Burnt Stand Road in Lumpkin County, Georgia.
The Auraria Road at Burnt Stand Road Roundabout project is initiated by the Lumpkin County Board of Commissioners. The project aims to enhance traffic flow and safety by constructing a four-leg roundabout at the intersection of Auraria Road and Burnt Stand Road, which also includes access to The White Oak Learning Academy.
This initiative is part of the county's commitment to improving local infrastructure using local funds while adhering to state and local construction laws.
Work Details
The work involves furnishing and installing all necessary materials, labor, tools, equipment, and related services for a complete project. Key components include:
- Construction of a complete four-leg roundabout intersection at Auraria Rd. and Burnt Stand Rd.
- Entrance road construction into The White Oak Learning Academy.
- Approximately 2,900 linear feet (L.F.) of roadway including:
- Asphalt pavement
- Concrete curb and gutter
- Concrete truck apron
- Sidewalks
- Driveway replacements
- Crosswalks
- Raised medians
- Signage and markings
- Storm drainage structures and piping
- Site grading, sodding, and erosion control in accordance with Contract Documents.
Period of Performance
The specific period of performance is not detailed in the provided solicitation text; however, it indicates that the work must be completed within a timeframe set forth in the Bid Form and Form of Agreement.
Place of Performance
The contract will be performed at the intersection of Auraria Road and Burnt Stand Road in Lumpkin County, Georgia.
Overview
Opportunity Type
Non-State Agency
Opportunity ID
63950 LUMPKIN PE-63950-NONST-2025-000000010
Response Deadline
March 20, 2025
Past Due
Date Posted
Feb. 19, 2025
Source
Est. Value Range
Experimental
$2,000,000 - $5,000,000
(AI estimate)
Agency Distribution
High
On 2/19/25 LUMPKIN COUNTY BOARD OF COMMISSIONERS in Georgia issued Non-State Agency Auraria Road At Burnt Stand Roundabout with ID 63950 LUMPKIN PE-63950-NONST-2025-000000010 due 3/20/25.
Contacts
Documents
Posted documents for Auraria Road At Burnt Stand Roundabout
Opportunity Assistant
AI Analysis
AI Generate
Classifications
Opportunity Classification
Construction / Public Works
Additional Details
Agency Site
Purchase Type
Non-State Agency