Background
The South Central Connecticut Regional Water Authority is issuing this Invitation to Bid (ITB) for the Lake Saltonstall Water Treatment Plant Gravity Thickener Improvements Project.
The goal of the contract is to enhance the functionality and efficiency of the water treatment facility through various upgrades and replacements.
Work Details
The project includes, but is not limited to:
- Replacement of the gravity thickener mechanism drive;
- Replacement of gravity thickener covers;
- Replacement of thickened sludge pumps and variable frequency drives (VFDs);
- Installation of new process piping and instrumentation;
- Preparation and painting of stairs, platforms, railings, beam bridge, gravity thickener exterior walls, gravity thickener interior steel and iron components, and pipes;
- Replacement of the thickened sludge flow meter;
- Replacement of the sludge fill station.
Period of Performance
The contract work is scheduled to commence on November 14, 2024, and will conclude on December 17, 2024.
Place of Performance
The work will be performed at the Lake Saltonstall Water Treatment Plant located in New Haven, Connecticut.
The South Central Connecticut Regional Water Authority is issuing this Invitation to Bid (ITB) for the Lake Saltonstall Water Treatment Plant Gravity Thickener Improvements Project.
The goal of the contract is to enhance the functionality and efficiency of the water treatment facility through various upgrades and replacements.
Work Details
The project includes, but is not limited to:
- Replacement of the gravity thickener mechanism drive;
- Replacement of gravity thickener covers;
- Replacement of thickened sludge pumps and variable frequency drives (VFDs);
- Installation of new process piping and instrumentation;
- Preparation and painting of stairs, platforms, railings, beam bridge, gravity thickener exterior walls, gravity thickener interior steel and iron components, and pipes;
- Replacement of the thickened sludge flow meter;
- Replacement of the sludge fill station.
Period of Performance
The contract work is scheduled to commence on November 14, 2024, and will conclude on December 17, 2024.
Place of Performance
The work will be performed at the Lake Saltonstall Water Treatment Plant located in New Haven, Connecticut.
Overview
Opportunity Type
ITB
Opportunity ID
26562
Response Deadline
Dec. 17, 2024
Past Due
Date Posted
Nov. 14, 2024
Source
Source Notes
Source does not have a linkable page for this opportunity. To find the opportunity, go to the Source website listed above and search for the opportunity title.
Est. Value Range
Experimental
$500,000 - $2,000,000
(AI estimate)
Agency Distribution
High
On 11/14/24 So. Central CT Regional Water Auth. in Connecticut issued ITB Lake Saltonstall Water Treatment Plant Gravity Thickener Improvements Project with ID 26562 due 12/17/24.
Contacts
Documents
Posted documents for Lake Saltonstall Water Treatment Plant Gravity Thickener Improvements Project
Opportunity Assistant
AI Analysis
AI Generate
Classifications
Additional Details
Who Can Respond
All Vendors