Question & Answer Assistant

Hello! Please let me know your questions about this opportunity. I will answer based on the available opportunity documents.

Sign in to upload a capability statement or catalogue for your company

Some suggestions:
Summarize the work to be completed under this opportunity
Does this solicitation list any subcontracting requirements?
List any requirements necessary to complete this contract
I'd like to anonymously submit a question to the procurement officer(s)
Loading
Get Real Time Alerts from 40k+ Federal, State and Local Agencies
Find Now

Description

The City of Los Angeles, Bureau of Engineering (BOE), is seeking a consultant to review plans and geotechnical reports, geotechnical observation and testing, geotechnical laboratory testing, and preparation of two certification (i.e. compaction) reports. *Any subconsultants that have been added to the contract and not originally a part of Schedule A must be registered with RAMP. **This TOS is only applicable to the top three firms on the Pre-Qualified On-Call Geotechnical and Environmental Engineering Services Consultants List: Geosyntec Consultants, Inc., Fugro USA Land, Inc., and Ninyo and Moore.
Background
The City of Los Angeles, through its Bureau of Engineering (BOE), is initiating a Task Order Solicitation (TOS) for the Griffith Park Performing Arts Center Project during its construction phase.

The BOE's Geotechnical Engineering Division (GED) is seeking a qualified consultant to provide essential geotechnical services, ensuring compliance with engineering standards and project specifications.

The project site is located at 4851 North Griffith Park Drive, Los Angeles, CA 90027.

Work Details
The consultant will be responsible for the following services:
1. **Observation and Testing**:
- Review plans and geotechnical reports.
- Confirm site preparation aligns with geotechnical recommendations.
- Collect soil samples for laboratory testing, including:
- Four (4) laboratory compaction tests (ASTM D1557)
- Four (4) sieve analysis tests (ASTM D6913)
- Four (4) expansion index tests (ASTM D4829)
- Confirm excavations reach minimum recommended depths.
- Observe exposed subgrade for suitability for backfill.
- Monitor installation of temporary shoring if required.
- Conduct fill placement and relative compaction tests using both nuclear gauge and sand cone methods, adhering to LADBS requirements.
- Ensure fill materials are free from debris and vegetation.
- Observe installation of retaining wall subdrains, footing excavations, cast-in-drilled-hole pile excavations, and pipe bedding operations.
- Submit daily reports summarizing construction activities and inspection results to GED.

2. **Compaction Certification Reports**: Two reports are required; the first draft within three working days post-earthwork completion beneath the outdoor stage structure, and the second draft after remaining earthwork completion. Each report must be reviewed by a California licensed Geotechnical Engineer before submission.

Period of Performance
The estimated duration for completing the tasks includes 45 full days (8 hours onsite each day) and 25 half days (4 hours onsite each day). A Deputy Grading Inspector will be required for 10 full-day visits and 10 half-day visits.

Place of Performance
The contract work will be performed at the Griffith Park Performing Arts Center site located at 4851 North Griffith Park Drive, Los Angeles, CA 90027.

Overview

Opportunity Type
TOS - Task Order Solicitation
Opportunity ID
219289
Response Deadline
Jan. 24, 2025 Past Due
Date Posted
Jan. 9, 2025
Est. Value Range
Experimental
$50,000 - $200,000 (AI estimate)
Agency Distribution
High
Source
On 1/9/25 Engineering Bureau, Public Works in California issued TOS - Task Order Solicitation Griffith Park Performing Arts Center Project - Construction Phase with ID 219289 due 1/23/25.

Contacts

Subscribe to find 500K+ key government decision markers

Free Trial Schedule Demo

Documents

Posted documents for TOS No. 13-068 Griffith Park Performing Arts Center Project - Construction Phase

Similar Active Opportunities