RFQP for Progressive Design-Build Services for Renovations of the CIty of Chula Vista's Civic Center and South Library Branches
ID: GGV0271 and GGV0272
• State: California
Opportunity Assistant
Loading
Description
Background
The City of Chula Vista is seeking Progressive Design-Build Services for the renovations of its Civic Center and South Library branches. The goal of this contract is to enhance the facilities to better serve the community, with a total project budget of $18,200,000.
Work Details
The contractor will provide comprehensive design-build services which include:
1) Preconstruction Fee - Lump Sum of $900,000;
2) Construction Phase Design Services calculated as 1.25% of the GMP Budget;
3) DBE’s General Requirements at 2.5% of the GMP Budget;
4) Overhead and Profit at 5.5% of the GMP Budget;
5) Insurance at 1.5% of the GMP Budget, exclusive of Builder’s Risk; and
6) Bonds at 1% of the GMP Budget.
The estimated base GMP will include construction costs, DBE contingency, DBE allowances, and City allowances.
Period of Performance
The specific period of performance is not detailed in the solicitation but will be determined based on project milestones and completion timelines as agreed upon in the contract.
Place of Performance
The work will be performed at the City of Chula Vista's Civic Center and South Library branches located in Chula Vista, California.
Bidder Requirements
Bidders are required to comply with all applicable regulations regarding Disadvantaged Business Enterprises (DBE). Specific requirements for certifications or registrations are not explicitly mentioned.
The City of Chula Vista is seeking Progressive Design-Build Services for the renovations of its Civic Center and South Library branches. The goal of this contract is to enhance the facilities to better serve the community, with a total project budget of $18,200,000.
Work Details
The contractor will provide comprehensive design-build services which include:
1) Preconstruction Fee - Lump Sum of $900,000;
2) Construction Phase Design Services calculated as 1.25% of the GMP Budget;
3) DBE’s General Requirements at 2.5% of the GMP Budget;
4) Overhead and Profit at 5.5% of the GMP Budget;
5) Insurance at 1.5% of the GMP Budget, exclusive of Builder’s Risk; and
6) Bonds at 1% of the GMP Budget.
The estimated base GMP will include construction costs, DBE contingency, DBE allowances, and City allowances.
Period of Performance
The specific period of performance is not detailed in the solicitation but will be determined based on project milestones and completion timelines as agreed upon in the contract.
Place of Performance
The work will be performed at the City of Chula Vista's Civic Center and South Library branches located in Chula Vista, California.
Bidder Requirements
Bidders are required to comply with all applicable regulations regarding Disadvantaged Business Enterprises (DBE). Specific requirements for certifications or registrations are not explicitly mentioned.
Loading Map
Loading Map
Overview
Agency
Opportunity Type
RFP (Request for Proposal)
Opportunity ID
GGV0271 and GGV0272
Response Deadline
Oct. 27, 2025
Past Due
Date Posted
Sept. 23, 2025
Source
Pre-Bid Conference
No
Est. Value Range
Experimental
$18,200,000
(Agency Estimate)
Agency Distribution
Low
On 9/23/25 City of Chula Vista in California issued RFP (Request for Proposal) Progressive Design-Build Services for Renovations of the City of Chula Vista's Civic Center and South Library Branches with ID GGV0271 and GGV0272 due 10/27/25.
Contacts
Documents
Posted documents for RFQP for Progressive Design-Build Services for Renovations of the CIty of Chula Vista's Civic Center and South Library Branches
Opportunity Assistant
AI Analysis
AI Generate
Additional Details
Other Details
See RFQP for details. This is a Prevailing Wage Project under the State of California Building Forward Grant.
Pre-bid meeting and walk-through at each site by 10/6/2025.
Pre-bid meeting and walk-through at each site by 10/6/2025.