Description
Background
The San Diego Unified School District (SDUSD) is seeking bids for the Standley Middle School Whole Site Modernization project, managed by Erickson-Hall Construction Co. Inc. The goal of this project is to modernize eight existing buildings at Standley Middle School, enhancing educational facilities and ensuring compliance with accessibility standards.
Work Details
The scope of work includes:
- Modernization of eight existing buildings with interior finishes and furniture, fixtures, and equipment (FF&E) upgrades.
- Accessibility upgrades.
- Re-roofing.
- Replacement of HVAC systems in all buildings.
- Construction of a new single point of entry with exterior glazing and a steel entrance canopy.
- Plumbing upgrades to food service building 100.
- Minor interior reconfigurations in buildings 200, 300, and 500.
- Site work including landscaping and accessibility upgrades.
- Removal of two existing portable classrooms.
- Installation of EV charging stations.
- Installation of eight temporary housing units on site for the duration of construction.
The project will be executed in seven phases under one Guaranteed Maximum Price (GMP).
Period of Performance
The contract period is scheduled from December 2025 to July 2028.
Place of Performance
The work will be performed at Standley Middle School located at 6298 Radcliffe Drive, San Diego, California.
Bidder Requirements
Bidders must be licensed contractors with A or B classifications or C specialty licenses relevant to the scope noted within the bid packages. Additionally, subcontractors must comply with the Project Stabilization Agreement (PSA) and meet a minimum participation percentage of 3% for Disabled Veteran Business Enterprises (DVBE). Prequalification applications are due by September 4, 2025. All subcontractors submitting bids over $50,000 must provide performance and payment bonds. Bidders must self-perform a minimum of 15% of each bid package.
The San Diego Unified School District (SDUSD) is seeking bids for the Standley Middle School Whole Site Modernization project, managed by Erickson-Hall Construction Co. Inc. The goal of this project is to modernize eight existing buildings at Standley Middle School, enhancing educational facilities and ensuring compliance with accessibility standards.
Work Details
The scope of work includes:
- Modernization of eight existing buildings with interior finishes and furniture, fixtures, and equipment (FF&E) upgrades.
- Accessibility upgrades.
- Re-roofing.
- Replacement of HVAC systems in all buildings.
- Construction of a new single point of entry with exterior glazing and a steel entrance canopy.
- Plumbing upgrades to food service building 100.
- Minor interior reconfigurations in buildings 200, 300, and 500.
- Site work including landscaping and accessibility upgrades.
- Removal of two existing portable classrooms.
- Installation of EV charging stations.
- Installation of eight temporary housing units on site for the duration of construction.
The project will be executed in seven phases under one Guaranteed Maximum Price (GMP).
Period of Performance
The contract period is scheduled from December 2025 to July 2028.
Place of Performance
The work will be performed at Standley Middle School located at 6298 Radcliffe Drive, San Diego, California.
Bidder Requirements
Bidders must be licensed contractors with A or B classifications or C specialty licenses relevant to the scope noted within the bid packages. Additionally, subcontractors must comply with the Project Stabilization Agreement (PSA) and meet a minimum participation percentage of 3% for Disabled Veteran Business Enterprises (DVBE). Prequalification applications are due by September 4, 2025. All subcontractors submitting bids over $50,000 must provide performance and payment bonds. Bidders must self-perform a minimum of 15% of each bid package.
Loading Map
Loading Map
Overview
Opportunity Type
Bid
Opportunity ID
LB25-0200-39-A1-G1
Response Deadline
Sept. 18, 2025
Past Due
Date Posted
Aug. 12, 2025
Source
Pre-Bid Conference
Yes - Not Mandatory 08/20/2025 2:00 PM (PDT) Standley Middle School, 6298 Radcliffe Dr., San Diego, CA 92122. Meet at East side of ADMIN Bldg. near Radcliffe Drive. All subcontractors are to park on the street. The meeting will begin with a general project overview, followed by a site walk of the school site.
Est. Value Range
Experimental
$15,000,000 - $25,000,000
(AI estimate)
Agency Distribution
High
On 8/12/25 San Diego Unified School District in California issued Bid Erickson-Hall Construction Co Bidding SDUSD Standley MS Whole Site Modernization with ID LB25-0200-39-A1-G1 due 9/18/25.
Contacts
Documents
Posted documents for Notice of Advertisement: Erickson-Hall Construction Co Bidding SDUSD Standley MS Whole Site Modernization GMP No. 1 (LLB)
Opportunity Assistant
AI Analysis
AI Generate
Additional Details
Other Details
See attached Invitation to Bid for the details of the bidding process. Erickson-Hall Construction Co. was previously awarded this Contract under solicitation Lb25-0200-39-A1-G1 and is the contractor bidding this Project. See contact information above for information related to this bid. **DO NOT CONTACT SDUSD.**
Estimated Bid Value
Project Estimate: $39,000,000.00