Tenova Wins $27 Million Army Contract for Rock Island Arsenal Furnace Modernization

HigherGov
11/20/2026 Contract Award Defense

Tenova Wins $27 Million Army Contract for Rock Island Arsenal Furnace Modernization
HigherGov

Tenova Inc. of Coraopolis, Pennsylvania, has won a firm-fixed-price Army contract with a total potential value of $26.5 million to modernize foundry equipment at Rock Island Arsenal–Joint Manufacturing and Technology Center. Awarded by Army Contracting Command, the work includes upgrading an existing furnace and replacing another with a new 5-ton electric arc furnace. The 5-Ton Electric Arc Furnace Project will be performed in Rock Island, Illinois, with estimated completion on Nov. 22, 2028. The solicitation designated the acquisition as a small-business set-aside.

5-Ton Electric Arc Furnace Project Details

Tenova will modernize an existing 5-ton electric arc furnace, remove a 3-ton electric arc furnace and install a new 5-ton replacement, according to the Army’s foundry equipment purchase description. The project also calls for a 5-ton argon oxygen decarburization system. The replacement furnace will have a rated capacity 2 tons greater than the unit it replaces, while the other furnace will retain its existing 5-ton rating.

The work extends from detailed design engineering and specification development through installation, commissioning and training. Tenova will provide project management, supporting equipment, concrete work and construction services needed to make the systems operational in Building 299. The contractor will also handle equipment-side utility connections, while Rock Island Arsenal will connect the facility’s utilities to the designated connection points.

The equipment will support a foundry that the Army describes as its only active foundry. Its work spans components for Army and joint-force requirements. In June 2024, the Army reported that the foundry had produced a 7,125-pound casting for a Corps of Engineers lock-and-dam system, its largest part in at least two decades. That production milestone illustrates the scale of work performed at the facility receiving the new and modernized equipment.

Award and Contractor Background

The Army received one bid after soliciting bids online. The solicitation issued July 15, 2026, identified Tenova as the intended sole-source recipient for the project. The Army obligated $14.7 million at award, establishing the initial commitment under the contract’s higher total potential value.


This award was disclosed by the DoW in its daily press release. Additional contract details will be available on HigherGov in approximately 90 days under W519TC27CA018 after the contract is formally disclosed by the government.