Martin Brothers Construction Wins $27 Million Army Reserve Microgrid Contract

HigherGov
11/17/2026 Contract Award Defense

Martin Brothers Construction Wins $27 Million Army Reserve Microgrid Contract
HigherGov

Martin Brothers Construction of Sacramento, California, has won a $26.7 million firm-fixed-price contract from the U.S. Army Corps of Engineers to build a microgrid at the Army Reserve’s 63rd Readiness Division headquarters campus in Mountain View, California. The Energy Resilience and Conservation Investment Program project will combine solar generation, battery storage and diesel backup power to sustain mission-critical functions for more than 14 days independently of the commercial electrical grid. The procurement was a total small-business set-aside, and construction is expected to be completed by Nov. 13, 2028.

63rd Readiness Division Microgrid Details

Martin Brothers will install a microgrid capable of operating autonomously while connected to the utility grid or in “island” mode, disconnected from it. Under normal conditions, the system will generate electricity alongside power supplied by PG&E and must transition seamlessly between connected and independent operation. A July 17 solicitation amendment identified the campus’s average electrical load as approximately 300 kilowatts, with a minimum of about 150 kilowatts and a peak near 600 kilowatts.

The generation and storage equipment will include a ground-mounted, 750-kilowatt-direct-current photovoltaic array south of the headquarters building, a 750-kilowatt-hour battery system with two 500-kilowatt inverters, and two 400-kilowatt diesel generators connected to a 10,000-gallon fuel tank. The project specifications also call for four generator quick-disconnect connections: two at the headquarters building and one each at the warehouse and maintenance shop.

Martin Brothers will build a new medium-voltage utility service feeding a new service disconnect and switchgear, along with replacement electrical connections serving the headquarters building. The switchgear and microgrid controller will occupy a climate-controlled enclosure. The contractor will coordinate the removal of existing electrical services and final utility permits with PG&E while the headquarters campus remains operational throughout construction.

A master microgrid controller and automatic smart switches will manage the campus’s generation resources. The control system will operate on a closed restricted network and must obtain an Army Authority to Operate, with cybersecurity measures meeting Defense Department requirements for facility-related control systems. The specifications also cover microgrid commissioning, electrical equipment testing, and operation and maintenance documentation.

Energy Resilience and Conservation Investment Program Background

ERCIP funds military infrastructure intended to improve energy resilience, efficiency and water resilience. The Defense Department’s annual energy resilience report describes an increasing use of microgrids, energy storage, renewable generation and cybersecurity improvements to address installation energy gaps. The Mountain View project combines those technologies with diesel generation to support extended operation during a utility outage.

The headquarters has a regional role in emergency continuity. An October 2020 Army account of the project described the 63rd Readiness Division as supporting Army Reserve readiness across seven states and identified earthquakes and wildfires as risks to commercial power. Maintaining electricity at Mountain View would allow headquarters personnel to continue operations and coordinate with subordinate units during a regional disruption.

Award and Contractor Background

The Corps received seven bids through an internet solicitation and awarded the contract on Nov. 12, 2026. The full contract amount was obligated at award. The construction solicitation, issued May 28, 2026, carried an estimated cost range of $10 million to $25 million; the award was approximately $1.7 million above that range’s upper limit.

The award follows several years of planning. In 2020, the Army expected construction to begin in late 2021 and the microgrid to enter operation in 2022 or 2023. A later Defense Department military-construction budget submission, with project data dated June 2025, estimated the Mountain View power-generation and microgrid project at $20.6 million. Those records document the project’s planning history; the November award establishes the construction contract with Martin Brothers.


This award was disclosed by the DoW in its daily press release. Additional contract details will be available on HigherGov in approximately 90 days under W9123827CA002 after the contract is formally disclosed by the government.