Search News & Reports

Korte Construction Wins $38 Million Army Corps Contract for Fort Gordon Barracks Replacement

HigherGov
11/20/2026 Contract Award Defense

Korte Construction Wins $38 Million Army Corps Contract for Fort Gordon Barracks Replacement
HigherGov

Korte Construction Co. has won a $38 million contract from the U.S. Army Corps of Engineers to design and construct two replacement barracks facilities at Fort Gordon, Georgia. The fixed-price-award-fee contract covers demolition and new construction under a design-build-to-budget approach, with completion expected by Sept. 26, 2029.

Fort Gordon Barracks Replacement Details

Korte will handle both design and construction for the two new barracks. The Army describes the work as “repair by replace,” making replacement construction, rather than renovation of existing rooms, the central scope of the project. Demolition is included in the same contract, placing that work alongside design and delivery of the new facilities.

The project will serve an installation where barracks are a central part of housing for junior enlisted soldiers. Under an August 2025 Fort Gordon housing policy, single soldiers in the rank of sergeant or below generally must live in barracks unless authorized to reside off post. The policy also requires installations to maintain 95% occupancy in single-soldier housing.

Award and Contractor Background

The Corps received 13 bids through an online competition. Its Savannah District is administering the contract, and the full $38 million was obligated at award.

Fort Gordon has a substantial history of barracks investment. In a March 2008 account of the Gordon Trainee Barracks Upgrade Project, the Army described an eight-year, $365 million effort to renovate 35 buildings, including 18 barracks, along with dining, headquarters and administrative facilities. That program focused on extending the useful life of older trainee facilities, whereas Korte’s award calls for replacement construction.

The same Army account described a $17.1 million phase awarded to Tetra Tech covering one barracks, a dining facility, a battalion headquarters and the 15th Signal Brigade headquarters. Completion of that phase was then expected by February 2009. The earlier work illustrates the installation’s use of multi-building renovation projects to sustain troop facilities; the new award places design, demolition and construction of two replacement barracks under one contractor.


This award was disclosed by the DoW in its daily press release. Additional contract details will be available on HigherGov in approximately 90 days under W912HN27CA004 after the contract is formally disclosed by the government.