The Utah Transit Authority (UTA) is submitting this application for $78,322,872 in FFY 2019 Section 5309 Small Starts CIG funds under discretionary ID D2019 SMST-010 for the Ogden/WSU Bus Rapid Transit (BRT) Project (hereafter Project).

The Project is a 5.3-mile Bus Rapid Transit (BRT) line connecting the Ogden FrontRunner commuter rail station to Weber State University (WSU) and McKay-Dee Hospital in Ogden, Utah. It includes construction of 2.2 miles of exclusive bus lanes from 32nd Street Harrison up to the Dee Events Center, a total of 13 uniquely branded stations, transit signal priority, and purchase of 11 electric vehicles. The Project also includes a new transit center on the WSU campus and expansion of UTA's existing Mount Ogden maintenance facility.

On weekdays, the service is planned to operate every 15 minutes from 4:30 AM to 8:00 AM and from 5:00 PM to 12:30 AM; and every 10 minutes from 8:00 AM to 5:00 PM. On weekends, service is planned to operate every 15 minutes headways on Saturdays from 8:30 AM to 11:00 PM and every 30 minutes on Sundays from 9:30 AM to 7:00 PM. In addition, when WSU is in session, UTA plans to operate an additional shuttle service every ten minutes within the campus (between WSU main campus and Dee Events Center stations only) from 8:00 AM to 2:00 PM. This essentially results in service every five minutes over this section of the line.

The revenue service date is 04/09/2024.

The total project cost is $120,496,726. Funding sources for the overall project include:

Federal sources:
- $78,322,872 in FFY 2019 Section 5309 Small Starts CIG funds (65% of the total CIG project cost).
- $5,648,450 in Federal Highway Administration (FHWA) Congestion Mitigation and Air Quality Program (CMAQ) funds.
- $3,250,000 in Surface Transportation Block Grant (STBG) funds.

These CMAQ and STBG federal funds and their required local match have been and will be executed in other grant agreements as follows. Because of this, the total project cost is not all in this grant agreement.
- $1,500,000 STBG in award UT-2020-012 (award total was $1,608,925 = $1,500,000 federal + $108,925 local). This grant agreement was awarded, drawn down, and closed.
- $4,500,000 2019 CMAQ/STBG - previously transferred to FTA - to be included in the draft grant agreement with the temporary FAIN # 1167-2021-9.
- $1,500,000 2021 CMAQ - transfer to FTA in progress. - to be included in the draft grant agreement with the temporary FAIN # 1167-2021-9.
- $1,398,450 2022 CMAQ - will be transferred to FTA in 2022 and will be added through an amendment to the draft grant agreement with the temporary FAIN # 1167-2021-9 once it's awarded.

State sources:
Utah Department of Transportation (UDOT) Transit Transportation Investment Funds (TTIF): $4,000,000
UDOT cash contributions: $50,000

Local sources:
Utah Transit Authority Proposition 1 sales tax revenue funds: $12,555,404
Weber County Transportation sales and use tax revenues: $7,500,000
Ogden City sales tax revenues: $4,100,000

Private sector/in-kind sources:
UDOT right-of-way donations: $2,695,000
WSU right-of-way donations: $1,415,000
Rocky Mountain Power grant funds: $500,000
McKay-Dee Hospital right-of-way donations: $320,000
Ogden City right-of-way donations: $140,000

The total cost of the scope of work included in this grant is $110,952,103, made up of the $78,322,872 in CIG federal funds and $33,275,404 of non-federal funds, the local funds from Utah Transit Authority Proposition 1 sales tax revenues, funds Weber County Transportation sales and use tax revenues, Ogden City sales tax revenues, UDOT Transit Transportation Investment Funds, UDOT right-of-way donations, WSU right-of-way donations, Rocky Mountain Power grant funds, McKay-Dee Hospital right-of-way donations, Ogden City right-of-way donations, and UDOT cash contributions.

Award reporting: UTA is required to submit quarterly reports in TRAMS. FFRs and MPRs must be submitted and are due to FTA within 30 days after the end of each quarter, i.e., by January 30, April 30, July 30, and October 30. The FTA Regional Office may request more frequent reporting or additional reports if circumstances warrant additional reporting. UTA will follow all reporting requirements in accordance with FTA C 5010.1E, 2 CFR Part 200, and the project's PMP. This includes, but is not limited to, UTA notifying FTA Region 8 of all schedule changes and the reasons for the change reported quarterly to FTA through the Milestone Progress Report. Project schedules, budgets, change orders, status of procurements must be uploaded in TRAMS to this award. A copy of any updates to the Ogden/Weber State University Bus Rapid Transit project's PMP must be reported on a quarterly basis. An update to the PMP may be required anytime there is a significant change, such as key personnel leaving the project, transition through major milestones, and/or significant scope/cost/schedule changes. UTA must notify FTA of any unforeseen events that could impact the schedule, cost, capacity, usefulness, or purpose of the award. Including the terms and conditions applicable to the award must be reported to FTA immediately and then reflected in the next Milestone Progress Report.
Awarding Agency
Place of Performance
Utah United States
Geographic Scope
State-Wide
Related Opportunity
None
Analysis Notes
Amendment Since initial award the total obligations have decreased 6% from $110,952,103 to $104,697,920.
Utah Transit Authority was awarded Ogden/WSU Bus Rapid Transit Project: $78M Small Starts CIG Application Project Grant UT-2021-021 worth $78,322,872 from the FTA Office of Budget and Policy in September 2021 with work to be completed primarily in Utah United States. The grant has a duration of 3 years 3 months and was awarded through assistance program 20.500 Federal Transit Capital Investment Grants. $26,375,048 (25.0%) of this Project Grant was funded by non-federal sources.

Status
(Complete)

Last Modified 9/5/23

Period of Performance
9/24/21
Start Date
12/30/24
End Date
100% Complete

Funding Split
$78.3M
Federal Obligation
$26.4M
Non-Federal Obligation
$104.7M
Total Obligated
75.0% Federal Funding
25.0% Non-Federal Funding

Activity Timeline

Interactive chart of timeline of amendments to UT-2021-021

Transaction History

Modifications to UT-2021-021

Additional Detail

Award ID FAIN
UT-2021-021
SAI Number
UT-2021-021-01-20.500
Award ID URI
SAI NOT AVAILABLE
Awardee Classifications
Other
Awarding Office
6982SY REGION 8 DOT FTA
Funding Office
693JJ8 OFFICE OF BUDGET AND POLICY(TBP)
Awardee UEI
PQ4YJL6FKFX6
Awardee CAGE
1G5T5
Performance District
UT-01
Senators
Mike Lee
Mitt Romney
Modified: 9/5/23