The recipients purpose is to complete planning, design, and construction activities for a regional reuse system.
The goal is to integrate a potable and secondary irrigation reuse source into Washington County's water supply portfolio to help meet water demand for the area's expanding economy and growing population.
The recipient shall plan, design and construct a regional reuse system in Washington County.
The regional reuse system comprises multiple phases of treatment, conveyance, and storage projects.
The project activities include project planning, 30% design, 100% design, and construction stages.
The following tasks will be completed:
Task 1, complete site-specific geotechnical and survey studies to gather design data.
Task 2, refine preliminary project designs and cost estimates.
Task 3, initiate environmental compliance and other related permitting activities.
Task 4, compile and or complete baseline environmental and cultural resources studies.
Task 5, prepare construction drawings and specifications and a design report to 30% level.
Task 6, prepare construction drawings and specifications and a design report to 100% level.
Task 7, obtain bids and select contractor to complete construction activities.
The goal is to integrate a potable and secondary irrigation reuse source into Washington County's water supply portfolio to help meet water demand for the area's expanding economy and growing population.
The recipient shall plan, design and construct a regional reuse system in Washington County.
The regional reuse system comprises multiple phases of treatment, conveyance, and storage projects.
The project activities include project planning, 30% design, 100% design, and construction stages.
The following tasks will be completed:
Task 1, complete site-specific geotechnical and survey studies to gather design data.
Task 2, refine preliminary project designs and cost estimates.
Task 3, initiate environmental compliance and other related permitting activities.
Task 4, compile and or complete baseline environmental and cultural resources studies.
Task 5, prepare construction drawings and specifications and a design report to 30% level.
Task 6, prepare construction drawings and specifications and a design report to 100% level.
Task 7, obtain bids and select contractor to complete construction activities.
Awardee
Funding Goals
MANAGE, DEVELOP, AND PROTECT WATER AND RELATED RESOURCES IN AN ENVIRONMENTALLY AND ECONOMICALLY SOUND MANNER IN THE INTEREST OF THE AMERICAN PUBLIC.
Grant Program (CFDA)
Funding Agency
Place of Performance
Utah
United States
Geographic Scope
State-Wide
County Of Washington was awarded
Regional Reuse System Development in Washington County
Project Grant R25AP00102
worth $20,539,640
from the Bureau of Reclamation in July 2025 with work to be completed primarily in Utah United States.
The grant
has a duration of 4 years 5 months and
was awarded through assistance program 15.504 Title XVI Water Reclamation and Reuse.
$61,684,620 (75.0%) of this Project Grant was funded by non-federal sources.
The Project Grant was awarded through grant opportunity WaterSMART: Large-Scale Water Recycling Projects for Fiscal Years 2023 and 2024.
Status
(Ongoing)
Last Modified 8/1/25
Period of Performance
7/17/25
Start Date
12/31/29
End Date
Funding Split
$20.5M
Federal Obligation
$61.7M
Non-Federal Obligation
$82.2M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
R25AP00102
SAI Number
None
Award ID URI
None
Awardee Classifications
Special District Government
Awarding Office
140R40 UPPER COLORADO REGIONAL OFFICE
Funding Office
140R81 DENVER FED CENTER
Awardee UEI
JJESCN8CM5P4
Awardee CAGE
3L4Z8
Performance District
UT-02
Senators
Mike Lee
Mitt Romney
Mitt Romney
Modified: 8/1/25