NY-2023-106
Project Grant
Overview
Grant Description
Application purpose: The purpose is to construct the Second Avenue Subway Phase 2 project.
Activities performed: The project includes the construction of three new stations, traction power substations, signal track communication systems, and station architectural elements and facilities.
Expected outcomes: The Second Avenue Subway (SAS) Phase 2 project (project) is a planned two-track 1.76-mile heavy rail subway extension along the east side of Manhattan.
It will connect the northern end of Phase 1 at 105th Street to the 125th Street station of the Lexington Avenue Line and terminate west of the intersection of Malcolm X Boulevard and 125th Street.
Intended beneficiaries: Commuters along Manhattan's east side and users of the MTA subway system.
Subrecipient activities: There are no sub-recipient activities with this award.
Activities performed: The project includes the construction of three new stations, traction power substations, signal track communication systems, and station architectural elements and facilities.
Expected outcomes: The Second Avenue Subway (SAS) Phase 2 project (project) is a planned two-track 1.76-mile heavy rail subway extension along the east side of Manhattan.
It will connect the northern end of Phase 1 at 105th Street to the 125th Street station of the Lexington Avenue Line and terminate west of the intersection of Malcolm X Boulevard and 125th Street.
Intended beneficiaries: Commuters along Manhattan's east side and users of the MTA subway system.
Subrecipient activities: There are no sub-recipient activities with this award.
Funding Goals
THE CAPITAL INVESTMENT GRANT (CIG) AND EXPEDITED PROJECT DELIVERY PILOT PROGRAMS PROVIDE FUNDING FOR FIXED GUIDEWAY INVESTMENTS SUCH AS NEW AND EXPANDED RAPID RAIL COMMUTER RAIL LIGHT RAIL STREETCARS BUS RAPID TRANSIT AND FERRIES AS WELL AS CORRIDOR-BASED BUS RAPID TRANSIT INVESTMENTS THAT EMULATE THE FEATURES OF RAIL.
Grant Program (CFDA)
Awarding Agency
Funding Agency
Place of Performance
New York
United States
Geographic Scope
State-Wide
Related Opportunity
NOT APPLICABLE
Analysis Notes
Amendment Since initial award the total obligations have increased 81% from $1,103,307,646 to $2,001,251,016.
Metropolitan Transportation Authority was awarded
Phase 2 Second Avenue Subway Extension: Enhancing Commuter Access in Manhattan
Project Grant NY-2023-106
worth $946,784,764
from the FTA Office of Budget and Policy in November 2023 with work to be completed primarily in New York United States.
The grant
has a duration of 9 years 10 months and
was awarded through assistance program 20.500 Federal Transit Capital Investment Grants.
$1,054,466,252 (53.0%) of this Project Grant was funded by non-federal sources.
Status
(Ongoing)
Last Modified 9/16/24
Period of Performance
11/4/23
Start Date
9/30/33
End Date
Funding Split
$946.8M
Federal Obligation
$1.1B
Non-Federal Obligation
$2.0B
Total Obligated
Activity Timeline
Transaction History
Modifications to NY-2023-106
Additional Detail
Award ID FAIN
NY-2023-106
SAI Number
NY-2023-106-01-20.500
Award ID URI
SAI EXEMPT
Awardee Classifications
Other
Awarding Office
692387 REGION 2 DOT FTA
Funding Office
693JJ8 OFFICE OF BUDGET AND POLICY(TBP)
Awardee UEI
NXGWYMXLNW95
Awardee CAGE
4JQ71
Performance District
NY-90
Senators
Kirsten Gillibrand
Charles Schumer
Charles Schumer
Modified: 9/16/24