DECD0000051
Cooperative Agreement
Overview
Grant Description
1. Design, build, and commence operations of a solvent-based post combustion carbon capture system to separate carbon dioxide (CO2) from a stream at Vicksburg Pulp and Paper Mill Facility (120,000 T-CO2/year) and validate at least 90% carbon capture efficiency and 95% CO2 purity under real exhaust conditions, for at least 2,000 hours of continuous steady-state operation.
2. Achieve DOE Technology Readiness Level (TRL) 7 for solvent-based post combustion carbon capture technology by the completion of the performance period.
3. Complete at least one (1) year of large-scale pilot testing of a carbon capture technology under real exhaust conditions (e.g., normal steady-state [at least 2,000 hours] and dynamic operations) covering the full spectrum of performance conditions, meeting key technical performance targets, and collect required data to quantify other project benefits or negative impacts.
4. Achieve at least 2,000 hours of continuous operation under stable conditions at performance targets that can enable validation of a commercial-scale process using techno-economic analysis (TEA) & life cycle analysis (LCA) models that are informed with data from the testing.
2. Achieve DOE Technology Readiness Level (TRL) 7 for solvent-based post combustion carbon capture technology by the completion of the performance period.
3. Complete at least one (1) year of large-scale pilot testing of a carbon capture technology under real exhaust conditions (e.g., normal steady-state [at least 2,000 hours] and dynamic operations) covering the full spectrum of performance conditions, meeting key technical performance targets, and collect required data to quantify other project benefits or negative impacts.
4. Achieve at least 2,000 hours of continuous operation under stable conditions at performance targets that can enable validation of a commercial-scale process using techno-economic analysis (TEA) & life cycle analysis (LCA) models that are informed with data from the testing.
Awardee
Funding Goals
CARBON CAPTURE PILOT AT VICKSBURG CONTAINERBOARD MILL
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Redwood,
Mississippi
39156-0358
United States
Geographic Scope
Single Zip Code
Related Opportunity
Analysis Notes
Termination This cooperative agreement was reported on the Department of Government Efficiency (DOGE) partial or complete termation list as of its last report October 2025. See All
Research Triangle Institute was awarded
Solvent-Based Carbon Capture System for Vicksburg Pulp & Paper Mill
Cooperative Agreement DECD0000051
worth $4,304,715
from the Department of Energy in September 2024 with work to be completed primarily in Redwood Mississippi United States.
The grant
has a duration of 6 years 6 months and
was awarded through assistance program 81.255 Clean Energy Demonstrations.
$2,084,797 (33.0%) of this Cooperative Agreement was funded by non-federal sources.
The Cooperative Agreement was awarded through grant opportunity Bipartisan Infrastructure Law Carbon Capture Large-Scale Pilot Projects Funding Opportunity Announcement.
Status
(Ongoing)
Last Modified 7/22/25
Period of Performance
9/25/24
Start Date
3/30/31
End Date
Funding Split
$4.3M
Federal Obligation
$2.1M
Non-Federal Obligation
$6.4M
Total Obligated
Activity Timeline
Subgrant Awards
Disclosed subgrants for DECD0000051
Transaction History
Modifications to DECD0000051
Additional Detail
Award ID FAIN
DECD0000051
SAI Number
None
Award ID URI
SAI EXEMPT
Awardee Classifications
Nonprofit With 501(c)(3) IRS Status (Other Than An Institution Of Higher Education)
Awarding Office
892436 OFFICE OF CLEAN ENERGY DEMONSTRATIONS (OCED)
Funding Office
892410 OFFICE OF CLEAN ENERGY DEMONSTRATION
Awardee UEI
JJHCMK4NT5N3
Awardee CAGE
3A730
Performance District
MS-02
Senators
Roger Wicker
Cindy Hyde-Smith
Cindy Hyde-Smith
Modified: 7/22/25