The overall objective of the project is to perform the preliminary development work for an integrated CO2 capture and storage project at the Mitchell cement plant. During the proposed project, the team will apply its extensive knowledge base, built from previous feed studies, to complete the conceptual design of a carbon capture system capable of capturing a minimum of 95% of the CO2 emissions.

The feed study for the CO2 capture system will include significant design deliverables consistent with the level needed to develop an AACE Class 3 estimate with an accuracy of ±15%. For the entire scope of the capture facility and balance of plant systems and will expand upon the work being completed under FECM FOA-2515 (DE-FE0032222).

In addition to the feed study for the CO2 capture system, the project team will develop a feed study for the CO2 pipeline and a storage field development plan to permanently sequester the captured CO2 onsite under FECM FOA 2610, DE-FE0032268. The development of the major permits needed for the integrated CO2 capture project to move forward, such as the air permit and Class VI well permit to construct will be included in this project scope of work.

Capture, transport, and storage plans will be integrated in the scope of this project, pending deliverables of final feed studies and site characterization from (DE-FE0032222 and DE-FE0032268). The proposed project also includes execution of the Community Benefits Plan (CBP).

The completed feed study will include the design of a cost-effective carbon capture and storage (CCS) system for a state-of-the-art, energy-efficient cement facility with extremely low emissions. In addition, to advancing this project to be ready for the next phase, this feed study will demonstrate that CO2 capture can be integrated into new and existing cement plants.
Funding Goals
HEIDELBERG MATERIALS US INC. PROJECT TITLE: MITCHELL CEMENT PLANT INTEGRATED CO2 CAPTURE PROJECT
Awarding / Funding Agency
Place of Performance
Mitchell, Indiana 47446-6869 United States
Geographic Scope
Single Zip Code
Analysis Notes
Infrastructure $4,992,811 (100%) percent this Cooperative Agreement was funded by the 2021 Infrastructure Act.
Heidelberg Materials Us was awarded Integrated CO2 Capture and Storage Project for Mitchell Cement Plant Cooperative Agreement DECD0000009 worth $4,992,811 from the Department of Energy in October 2023 with work to be completed primarily in Mitchell Indiana United States. The grant has a duration of 2 years and was awarded through assistance program 81.255 Clean Energy Demonstrations. $3,157,637 (39.0%) of this Cooperative Agreement was funded by non-federal sources. The Cooperative Agreement was awarded through grant opportunity BIL: Carbon Capture Demonstration Projects Program FRONT-END ENGINEERING DESIGN STUDIES FOR INTEGRATED CARBON CAPTURE, TRANSPORT and STORAGE SYSTEMS.

Status
(Complete)

Last Modified 6/3/25

Period of Performance
10/1/23
Start Date
9/30/25
End Date
100% Complete

Funding Split
$5.0M
Federal Obligation
$3.2M
Non-Federal Obligation
$8.2M
Total Obligated
61.0% Federal Funding
39.0% Non-Federal Funding

Activity Timeline

Interactive chart of timeline of amendments to DECD0000009

Subgrant Awards

Disclosed subgrants for DECD0000009

Transaction History

Modifications to DECD0000009

Additional Detail

Award ID FAIN
DECD0000009
SAI Number
None
Award ID URI
SAI EXEMPT
Awardee Classifications
For-Profit Organization (Other Than Small Business)
Awarding Office
892436 OFFICE OF CLEAN ENERGY DEMONSTRATIONS (OCED)
Funding Office
892410 OFFICE OF CLEAN ENERGY DEMONSTRATION
Awardee UEI
MTGUMQLV8ZZ1
Awardee CAGE
7PTC4
Performance District
IN-09
Senators
Todd Young
Mike Braun

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Clean Energy Demonstrations, Energy Programs, Energy (089-2297) Energy conservation Grants, subsidies, and contributions (41.0) $4,992,811 100%
Modified: 6/3/25