Application purpose: This request is to allocate $39,822,803 in FY23 5309 supplemental capital investment funds to BART's core capacity project.
These funds will be used to supplant local BART funds;
Activities performed: This project aims to upgrade BART's system and rolling stock to accommodate increased system capacity including design and construction of the Transbay Corridor core capacity project;
Expected outcomes: Prove safe and reliable transit to the San Francisco Bay Area region and increased service and transit capacity in the San Francisco Transbay Corridor;
Intended beneficiaries: BART serves the public in and around the San Francisco Bay Area;
Subrecipient activities: None.
These funds will be used to supplant local BART funds;
Activities performed: This project aims to upgrade BART's system and rolling stock to accommodate increased system capacity including design and construction of the Transbay Corridor core capacity project;
Expected outcomes: Prove safe and reliable transit to the San Francisco Bay Area region and increased service and transit capacity in the San Francisco Transbay Corridor;
Intended beneficiaries: BART serves the public in and around the San Francisco Bay Area;
Subrecipient activities: None.
Funding Goals
FUND SUBSTANTIAL CORRIDOR-BASED INVESTMENT IN EXISTING FIXED GUIDEWAY SYSTEMS WHERE THE PROJECT IS LOCATED INA CORRIDOR THAT IS AT OR OVER CAPACITY OR WILL BE IN TENYEARS AND WILL INCREASE CAPACITY BY 10% AND DOES NOT INCLUDE PROJECT ELEMENTS DESIGNATED TO MAINTAIN A STATE OF GOOD REPAIR.
Grant Program (CFDA)
Awarding Agency
Funding Agency
Place of Performance
California
United States
Geographic Scope
State-Wide
Related Opportunity
NOT APPLICABLE
San Francisco Bay Area Rapid Transit District was awarded
BART Core Capacity Project for SF Bay Area Transit
Project Grant CA-2025-064
worth $39,822,803
from the FTA Office of Budget and Policy in May 2025 with work to be completed primarily in California United States.
The grant
has a duration of 9 years and
was awarded through assistance program 20.500 Federal Transit Capital Investment Grants.
Status
(Ongoing)
Last Modified 5/12/25
Period of Performance
5/5/25
Start Date
5/30/34
End Date
Funding Split
$39.8M
Federal Obligation
$0.0
Non-Federal Obligation
$39.8M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
CA-2025-064
SAI Number
CA-2025-064-00-20.500
Award ID URI
SAI NOT AVAILABLE
Awardee Classifications
Special District Government
Awarding Office
699J58 REGION 9 DOT FTA
Funding Office
693JJ8 OFFICE OF BUDGET AND POLICY(TBP)
Awardee UEI
K7KGWMHLN1N1
Awardee CAGE
44PR7
Performance District
CA-90
Senators
Dianne Feinstein
Alejandro Padilla
Alejandro Padilla
Modified: 5/12/25