This application is to request FY2021 Section 5339(b) funds apportioned to the State of California UZA (60020) in the amount of $3,530,822.

FY 2021 Section 5339(b) State of California UZA (60000): $3,530,822

Total Federal Funding (D2022-BUSC-012): $3,530,822

Overall Grant Funding:
Federal Funds 78%
FY 2021 Section 5339(b): $3,530,822
Total Federal Funds: $3,530,822

Local Match 22%
Prop A Local Return: $995,873
Total Local Match: $995,873
Total Project Cost: $4,526,695

Purpose:
The purpose of this award is to provide 3 replacement BEBs and associated e-charging infrastructure, including project administration.

Activities to be performed:
Funds will cover charges associated with the acquisition of 3 BEBs, e-charging infrastructure, and associated project administration of award D2022-BUSC-012.

Expected Outcomes:
Funding will allow for the timely replacement of vehicles that have exceeded their useful life, as well as support NTSS goal of zero emissions by 2040.

Intended Beneficiaries:
This project will benefit the patrons of the Norwalk Transit System, the City of Norwalk, and the surrounding Gateway Cities NTS services.

Subrecipient Activities:
None

The City of Norwalk was awarded $3,530,822 in FFY21 5339(b) Buses and Bus Facilities (D2022-BUSC-012). The City of Norwalk (Norwalk Transportation System) is hereby submitting this grant application in support of the following capital projects:

1) Purchase (3) Zero Emission Battery-Electric Buses:
This grant applies $2,749,500 in FY21 Section 5339 funds for bus replacement. The City of Norwalk will purchase 3 low floor-40 ft. zero emissions battery-electric buses to replace three (3) New Flyer hybrid buses. The three (3) New Flyer hybrid (gasoline/electric) buses that are being replaced were all manufactured in 2010 by New Flyer GE 35LFR buses. Bus numbers and mileage are as follows:
- Bus #7092 - 310,590 miles
- Bus #7093 - 372,632 miles
- Bus #7094 - 337,377 miles
All replacement buses have met FTAs useful life of 12 years. The new buses will have an expected useful life of 12 years and/or 500,000 miles and will meet the Clean Air Act standards (CAA) and the Americans with Disabilities Act (ADA) requirements.

2) Purchase (3) Charging Stations and Associated Infrastructure Costs:
This grant applies $625,322 in FY21 Section 5339 funds to purchase 3 charging stations and corresponding infrastructure costs associated with supporting the acquisition of 3 ZEB buses.

3) Project Administration:
This grant applies $156,000 in FY21 Section 5339 funds toward the project administration of awarded project D2022-BUSC-012.
Awardee
Awarding Agency
Place of Performance
California United States
Geographic Scope
State-Wide
Related Opportunity
None
City Of Norwalk was awarded Replacement BEBs E-Charging Infrastructure Norwalk Transit System Project Grant CA-2022-112 worth $3,530,822 from the FTA Office of Budget and Policy in August 2022 with work to be completed primarily in California United States. The grant has a duration of 1 year 1 months and was awarded through assistance program 20.526 Buses and Bus Facilities Formula, Competitive, and Low or No Emissions Programs. $995,873 (22.0%) of this Project Grant was funded by non-federal sources.

Status
(Complete)

Last Modified 8/15/22

Period of Performance
8/12/22
Start Date
9/30/23
End Date
100% Complete

Funding Split
$3.5M
Federal Obligation
$995.9K
Non-Federal Obligation
$4.5M
Total Obligated
78.0% Federal Funding
22.0% Non-Federal Funding

Activity Timeline

Interactive chart of timeline of amendments to CA-2022-112

Additional Detail

Award ID FAIN
CA-2022-112
SAI Number
CA-2022-112-00-20.526
Award ID URI
SAI EXEMPT
Awardee Classifications
City Or Township Government
Awarding Office
699J58 REGION 9 DOT FTA
Funding Office
693JJ8 OFFICE OF BUDGET AND POLICY(TBP)
Awardee UEI
WN2HYD8YB3H5
Awardee CAGE
39KN6
Performance District
90
Senators
Dianne Feinstein
Alejandro Padilla

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Formula and Bus Grants, Liquidation of Contract Authorization, Federal Transit Administration, Transportation (069-8350) Ground transportation Grants, subsidies, and contributions (41.0) $3,530,822 100%
Modified: 8/15/22