Description: This agreement provides funding to the Town of West Union, WV, to implement its project for wastewater treatment plant and system upgrades as directed in the 2024 Consolidated Appropriations Act or as identified in an approved technical correction if one has been approved for this project.
Activities: The activities to be performed include the execution and implementation of a wastewater infrastructure construction project.
Workplan activities consist of: demolition of the existing undersized and deteriorating wastewater treatment plant (WWTP), construction of a new 750,000 gallon per day (GPD) WWTP, and eventually a new wastewater pump station to sufficiently accommodate additional requested flows from the nearby regional jail.
Subrecipient: No subawards are included in this assistance agreement.
Outcomes: The anticipated deliverables include improvements consisting of the construction of a new 750,000 gallons per day (GPD) wastewater treatment plant (WWTP), demolition of the existing WWTP, approximately 50 linear feet of gravity sewer pipe, and three sanitary sewer manholes.
One new pump station at the regional jail is included as a contingent item that is not necessary for the WWTP improvements, but part of the overall improvement plans.
The expected outcomes include fewer overflow events in the West Union collection system, as well as a higher quality of effluent discharged, improving the water quality of Middle Island Creek.
The intended beneficiaries include the Town of West Union, nearby regional jail, and the communities downstream who rely on the water quality of Middle Island Creek.
Activities: The activities to be performed include the execution and implementation of a wastewater infrastructure construction project.
Workplan activities consist of: demolition of the existing undersized and deteriorating wastewater treatment plant (WWTP), construction of a new 750,000 gallon per day (GPD) WWTP, and eventually a new wastewater pump station to sufficiently accommodate additional requested flows from the nearby regional jail.
Subrecipient: No subawards are included in this assistance agreement.
Outcomes: The anticipated deliverables include improvements consisting of the construction of a new 750,000 gallons per day (GPD) wastewater treatment plant (WWTP), demolition of the existing WWTP, approximately 50 linear feet of gravity sewer pipe, and three sanitary sewer manholes.
One new pump station at the regional jail is included as a contingent item that is not necessary for the WWTP improvements, but part of the overall improvement plans.
The expected outcomes include fewer overflow events in the West Union collection system, as well as a higher quality of effluent discharged, improving the water quality of Middle Island Creek.
The intended beneficiaries include the Town of West Union, nearby regional jail, and the communities downstream who rely on the water quality of Middle Island Creek.
Awardee
Funding Goals
5 - ENSURE CLEAN AND SAFE WATER FOR ALL COMMUNITIES 5.1 - ENSURE SAFE DRINKING WATER AND RELIABLE WATER INFRASTRUCTURE
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
West Union,
West Virginia
United States
Geographic Scope
City-Wide
Related Opportunity
EPA-CEP-01
Town Of West Union Town Hall was awarded
West Union Wastewater Treatment Plant Upgrade Grant
Cooperative Agreement 953A0053
worth $10,022,000
from EPA Region 3: Philadelphia in April 2025 with work to be completed primarily in West Union West Virginia United States.
The grant
has a duration of 1 year 7 months and
was awarded through assistance program 66.202 Congressionally Mandated Projects.
$2,505,500 (20.0%) of this Cooperative Agreement was funded by non-federal sources.
Status
(Ongoing)
Last Modified 5/1/25
Period of Performance
4/23/25
Start Date
11/30/26
End Date
Funding Split
$10.0M
Federal Obligation
$2.5M
Non-Federal Obligation
$12.5M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
953A0053
SAI Number
None
Award ID URI
SAI EXEMPT
Awardee Classifications
City Or Township Government
Awarding Office
68HF03 REGION 3 (GRANTS OFFICE)
Funding Office
68S000 REGION 3 (FUNDING OFFICE)
Awardee UEI
CK2MZ3DU1UE7
Awardee CAGE
7MFS6
Performance District
WV-02
Senators
Joe Manchin
Shelley Capito
Shelley Capito
Modified: 5/1/25