69A36524521000CRSCA
Cooperative Agreement
Overview
Grant Description
1. Purpose: The project will separate and eliminate 7 at-grade crossings and advance completion of high-speed rail passenger service.
2. Activities: The project includes the following elements: administration and management of the project, administration and management of the construction, final design and construction of two overcrossings, four undercrossings, relocation of BNSF rail, and closure of one crossing and, right-of-way (ROW) acquisition for the project.
3. Deliverables:
- Task 1: Project administration and management
- Task 2: Final design
- Task 3: Construction
- Task 4: Construction management
- Task 5: Right-of-way acquisition
4. Beneficiary: The California High Speed Rail Authority is the grantee.
5. Subrecipient: None.
2. Activities: The project includes the following elements: administration and management of the project, administration and management of the construction, final design and construction of two overcrossings, four undercrossings, relocation of BNSF rail, and closure of one crossing and, right-of-way (ROW) acquisition for the project.
3. Deliverables:
- Task 1: Project administration and management
- Task 2: Final design
- Task 3: Construction
- Task 4: Construction management
- Task 5: Right-of-way acquisition
4. Beneficiary: The California High Speed Rail Authority is the grantee.
5. Subrecipient: None.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Shafter,
California
United States
Geographic Scope
City-Wide
California High-Speed Rail Authority was awarded
California High-Speed Rail Authority : Enhancing Rail Safety Efficiency
Cooperative Agreement 69A36524521000CRSCA
worth $201,946,942
from Federal Railroad Administration in September 2024 with work to be completed primarily in Shafter California United States.
The grant
has a duration of 6 years 6 months and
was awarded through assistance program 20.325 Consolidated Rail Infrastructure and Safety Improvements.
$89,873,197 (31.0%) of this Cooperative Agreement was funded by non-federal sources.
The Cooperative Agreement was awarded through grant opportunity FY22 Consolidated Rail Infrastructure and Safety Improvements Grant Program.
Status
(Ongoing)
Last Modified 9/16/24
Period of Performance
9/1/24
Start Date
3/31/31
End Date
Funding Split
$201.9M
Federal Obligation
$89.9M
Non-Federal Obligation
$291.8M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
69A36524521000CRSCA
SAI Number
None
Award ID URI
None
Awardee Classifications
State Government
Awarding Office
69A365 OFFICE OF FUNDS ADMINISTRA (GRANTS)
Funding Office
69A365 OFFICE OF FUNDS ADMINISTRA (GRANTS)
Awardee UEI
FJW5LSYDQLF3
Awardee CAGE
5QMN9
Performance District
CA-22
Senators
Dianne Feinstein
Alejandro Padilla
Alejandro Padilla