The purpose of this award is to fund a FY 2022-2023 Federal State Partnership Northeast Corridor Program grant for the Hudson Tunnel Project (the Project or HTP) to help achieve the goals identified in the Notice of Funding Opportunity for projects located on the Northeast Corridor for the Federal-State Partnership for Intercity Passenger Rail Grants Program, 87 Fed. Reg. 79421, December 27, 2022 that solicited applications for federal financial assistance.
The FSP-NEC Project consists of three elements:
1) The construction of a new Hudson River Tunnel between New York and New Jersey
2) The rehabilitation of the existing North River Tunnel under the Hudson River and
3) Long Island Rail Road (LIRR) emergency services building (ESB) utility relocation early work associated with the separately funded Hudson Yards Concrete Casing Section Three (3) Project.
Deliverables for the Project include a Project Management Plan (PMP), final design set(s), a Real Estate Acquisition Management Plan (RAMP), contractor proposals and executed contracts, contractor Buy America certification, and a contractor safety plan.
The intended beneficiary as a result of this project is the National Railroad Passenger Corporation (AMTRAK).
The FSP-NEC Project consists of three elements:
1) The construction of a new Hudson River Tunnel between New York and New Jersey
2) The rehabilitation of the existing North River Tunnel under the Hudson River and
3) Long Island Rail Road (LIRR) emergency services building (ESB) utility relocation early work associated with the separately funded Hudson Yards Concrete Casing Section Three (3) Project.
Deliverables for the Project include a Project Management Plan (PMP), final design set(s), a Real Estate Acquisition Management Plan (RAMP), contractor proposals and executed contracts, contractor Buy America certification, and a contractor safety plan.
The intended beneficiary as a result of this project is the National Railroad Passenger Corporation (AMTRAK).
Awardee
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Multi-State
United States
Geographic Scope
Multi-State
Related Opportunity
Analysis Notes
Amendment Since initial award the total obligations have increased 33% from $2,849,999,872 to $3,799,999,824.
Gateway Development Commission was awarded
Hudson Tunnel Project Grant for Northeast Corridor Rail Improvement
Project Grant 69A36524420700FSPNY
worth $2,849,999,869
from Federal Railroad Administration in September 2024 with work to be completed primarily in Multi-State United States.
The grant
has a duration of 16 years 7 months and
was awarded through assistance program 20.326 Federal-State Partnership for State of Good Repair.
$949,999,955 (25.0%) of this Project Grant was funded by non-federal sources.
The Project Grant was awarded through grant opportunity FY22-23 Federal-State Partnership for Intercity Passenger Rail Grant Program for projects located on the Northeast Corridor.
Status
(Ongoing)
Last Modified 11/25/24
Period of Performance
9/2/24
Start Date
4/30/41
End Date
Funding Split
$2.8B
Federal Obligation
$950.0M
Non-Federal Obligation
$3.8B
Total Obligated
Activity Timeline
Transaction History
Modifications to 69A36524420700FSPNY
Additional Detail
Award ID FAIN
69A36524420700FSPNY
SAI Number
None
Award ID URI
None
Awardee Classifications
State Government
Awarding Office
69A365 OFFICE OF FUNDS ADMINISTRA (GRANTS)
Funding Office
69A365 OFFICE OF FUNDS ADMINISTRA (GRANTS)
Awardee UEI
L3A1UJSRCT44
Awardee CAGE
9ATY0
Performance District
90
Modified: 11/25/24