The purpose of this grant is to modernize Hackensack Substation 42. This will be accomplished by constructing a new control house with modern equipment that is more reliable. Additionally, the control house will be designed to accommodate future expansion for additional traction power capacity at the substation.
The new control house will replace and consolidate both the existing control house located within the existing substation and the load-sharing metering functions housed in the pre-fabricated control house that sits adjacent to the existing substation. The new control house will also have capacity for controls and protection of an additional transformer at the substation.
Improvements will increase capacity, reliability, and resiliency to minimize downtime to railroad operations. Passengers, businesses, and local residents will benefit from the increased safety and reliability of infrastructure related to Substation 42.
The new control house will replace and consolidate both the existing control house located within the existing substation and the load-sharing metering functions housed in the pre-fabricated control house that sits adjacent to the existing substation. The new control house will also have capacity for controls and protection of an additional transformer at the substation.
Improvements will increase capacity, reliability, and resiliency to minimize downtime to railroad operations. Passengers, businesses, and local residents will benefit from the increased safety and reliability of infrastructure related to Substation 42.
Awardee
Funding Goals
THE PURPOSE OF THIS GRANT IS TO MODERNIZE HACKENSACK SUBSTATION 42. THIS WILL BE ACCOMPLISHED BY CONSTRUCTING A NEW CONTROL HOUSE WITH MODERN EQUIPMENT THAT IS MORE RELIABLE. ADDITIONALLY, THE CONTROL HOUSE WILL BE DESIGNED TO ACCOMMODATE FUTURE EXPANSION FOR ADDITIONAL TRACTION POWER CAPACITY AT THE SUBSTATION. THE NEW CONTROL HOUSE WILL REPLACE AND CONSOLIDATE BOTH THE EXISTING CONTROL HOUSE LOCATED WITHIN THE EXISTING SUBSTATION AND THE LOAD-SHARING METERING FUNCTIONS HOUSED IN THE PRE-FABRICATED CONTROL HOUSE THAT SITS ADJACENT TO THE EXISTING SUBSTATION.THE NEW CONTROL HOUSE WILL ALSO HAVE CAPACITY FOR CONTROLS AND PROTECTION OF AN ADDITIONAL TRANSFORMER AT THE SUBSTATION. IMPROVEMENTS WILL INCREASE CAPACITY, RELIABILITY, AND RESILIENCY TO MINIMIZE DOWNTIME TO RAILROAD OPERATIONS. PASSENGERS, BUSINESSES, AND LOCAL RESIDENTS WILL BENEFIT FROM THE INCREASED SAFETY AND RELIABILITY OF INFRASTRUCTURE RELATED TO SUBSTATION 42.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
North Bergen,
New Jersey
United States
Geographic Scope
City-Wide
Amtrak was awarded
Modernizing Hackensack Substation 42 for Increased Rail Safety
Project Grant 69A36523420000SANDC
worth $10,463,791
from Federal Railroad Administration in July 2023 with work to be completed primarily in North Bergen New Jersey United States.
The grant
has a duration of 2 years 5 months and
was awarded through assistance program 20.323 Fiscal Year 2013 Hurricane Sandy Disaster Relief Grants to the National Railroad Passenger Corporation.
The Project Grant was awarded through grant opportunity FY23 Hackensack Substation #42 Resiliency Improvements Project (“Sub 42”).
Status
(Ongoing)
Last Modified 10/2/23
Period of Performance
7/1/23
Start Date
12/31/25
End Date
Funding Split
$10.5M
Federal Obligation
$0.0
Non-Federal Obligation
$10.5M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
69A36523420000SANDC
SAI Number
None
Award ID URI
None
Awardee Classifications
For-Profit Organization (Other Than Small Business)
Awarding Office
69A365 OFFICE OF FUNDS ADMINISTRA (GRANTS)
Funding Office
69A365 OFFICE OF FUNDS ADMINISTRA (GRANTS)
Awardee UEI
M22USH2CHRG1
Awardee CAGE
1TXU3
Performance District
NJ-09
Senators
Robert Menendez
Cory Booker
Cory Booker
Budget Funding
| Federal Account | Budget Subfunction | Object Class | Total | Percentage |
|---|---|---|---|---|
| Grants to the National Railroad Passenger Corporation, Federal Railroad Administration, Transportation (069-0704) | Ground transportation | Grants, subsidies, and contributions (41.0) | $10,463,791 | 100% |
Modified: 10/2/23