Project title: US-70: Over Lake Texoma (ROOSEVELT BRIDGE) ::: Project description: US-70: Over Lake Texoma (ROOSEVELT BRIDGE)
Funding Goals
THE GOALS OF THE BIP ARE: 1) TO IMPROVE THE SAFETY, EFFICIENCY, AND RELIABILITY OF THE MOVEMENT OF PEOPLE AND FREIGHT OVER BRIDGES; 2) TO IMPROVE THE CONDITION OF BRIDGES IN THE UNITED STATES BY A) REDUCING THE NUMBER OF BRIDGES IN POOR CONDITION OR IN FAIR CONDITION AND AT RISK OF FALLING INTO POOR CONDITION WITHIN THE NEXT 3 YEARS, B) REDUCING THE TOTAL PERSON MILES TRAVELED OVER BRIDGES IN POOR CONDITION, OR IN FAIR CONDITION AND AT RISK OF FALLING INTO POOR CONDITION WITHIN THE NEXT 3 YEARS, C) REDUCING THE NUMBER OF BRIDGES THAT DO NOT MEET CURRENT GEOMETRIC DESIGN STANDARDS, OR CANNOT MEET THE LOAD AND TRAFFIC REQUIREMENTS TYPICAL OF THE REGIONAL TRANSPORTATION NETWORK, AND D) REDUCING THE TOTAL PERSON MILES TRAVELED OVER BRIDGES THAT DO NOT MEET CURRENT GEOMETRIC DESIGN STANDARDS, OR CANNOT MEET THE LOAD AND TRAFFIC REQUIREMENTS TYPICAL OF THE REGIONAL TRANSPORTATION NETWORK; 3) TO PROVIDE FINANCIAL ASSISTANCE THAT LEVERAGES AND ENCOURAGES NON-FEDERAL CONTRIBUTIONS FROM SPONSORS AND STAKEHOLDERS INVOLVED IN THE PLANNING, DESIGN, AND CONSTRUCTION OF ELIGIBLE PROJECTS.
Place of Performance
Bryan, Oklahoma United States
Geographic Scope
County-Wide
Analysis Notes
Amendment Since initial award the total obligations have increased 63% from $249,850,000 to $408,445,181.
Oklahoma Department Of Transportation was awarded Project Grant 693JJ22540009Y18COK022N269BIPS worth $123,850,000 from the FHWA Office of the Chief Financial Officer in September 2025 with work to be completed primarily in Oklahoma United States. The grant has a duration of 4 years 8 months and was awarded through assistance program 20.205 Highway Planning and Construction. $284,595,181 (70.0%) of this Project Grant was funded by non-federal sources. The Project Grant was awarded through grant opportunity Fiscal Year (FY) 2023 – 2026 Bridge Investment Program, Large Bridge Project Grants.

Status
(Ongoing)

Last Modified 8/12/26

Period of Performance
9/8/25
Start Date
5/31/30
End Date
21.0% Complete

Funding Split
$123.8M
Federal Obligation
$284.6M
Non-Federal Obligation
$408.4M
Total Obligated
30.0% Federal Funding
70.0% Non-Federal Funding

Activity Timeline

Interactive chart of timeline of amendments to 693JJ22540009Y18COK022N269BIPS

Transaction History

Modifications to 693JJ22540009Y18COK022N269BIPS

Additional Detail

Award ID FAIN
693JJ22540009Y18COK022N269BIPS
SAI Number
693JJ22540009Y18COK022N269BIPS00109502
Award ID URI
SAI EXEMPT
Awardee Classifications
State Government
Awarding Office
693JJ2 FHWA OFC OF THE CHIEF FIN OFFICER
Funding Office
693JJ2 FHWA OFC OF THE CHIEF FIN OFFICER
Awardee UEI
P14MNTH7JM37
Awardee CAGE
339V2
Performance District
OK-02
Senators
James Lankford
Markwayne Mullin