Overview
Grant Description
Award Purpose
The project adds new features to an existing cargo dock to include an open cell sheet pile bulkhead, fender piles, and breasting dolphins.
Additionally, the project will include a concrete roll on roll off (RORO) ramp, fill, armor rock mooring fenders, bullrail, bollards, and cleats.
Activities to be Performed
The HMIC cargo dock will consist of approximately 330 linear feet of sheet pile adjacent to and within the footprint of the existing gravel barge landing.
Approximately 542 sheet piles will make up an open cell structure and approximately 21,160 square feet (SF) and 23,220 cubic yards (CY) of armor rock, shot rock surfacing course, and concrete fill will be placed to make up the cargo dock.
The cargo dock will also include the installation of a barge RORO ramp on the dock deck, five fender piles, and three breasting dolphins—one southeast of the dock and two northwest of the dock.
The scope of work is broken up into the following elements under one component:
Element 1: Project Administration, Contract Administration, Environmental Permitting, Fabrication, and Construction Inspection Services.
Element 2: Construction of Marine Industrial Center Harbor Project, Construction Survey, Contractor Mobilization and Demobilization, Mine Uplands Fill Material Source, Stabilize Cut Area and Create Required Drainage, Sheet Pile Bulkhead Dock and RORO Ramp Install, approximately 330 linear feet of sheet pile to create the open cell structure, place and compact approximately 23,220 CY of engineering fill material behind the sheet piles, construct a 40 by 75 RORO barge ramp, breasting and mooring improvements, bulkhead fender assembly, bulkhead mooring bollards and cleats, ramp mooring bollards, bullrail and cleats, installation of 5 fender dolphins, installation of 3 barge breasting dolphins, lighting utility installation.
Deliverables
Expected outcomes, performance measures as outlined in the grant agreement, page 11, schedule H.
Measure Maritime.
Category and Description: Vessel Calls Measures the number of vessels calling to the project study area per year.
Must be reported in total and disaggregated by any of the following where applicable: vessel type (e.g., container, bulk, RORO, LNG), freight capacity, vessel length, or other.
Measurement frequency: Quarterly.
Measure Maritime.
Category and Description: Vessel Turn Time, average vessel turn time (hours), meaning the time between a vessel first reporting at the port to the time it departs, including berth waiting time and servicing time.
Measurement frequency: Quarterly.
Intended Beneficiary: City of Hoonah.
Subrecipient Activities: None.
The project adds new features to an existing cargo dock to include an open cell sheet pile bulkhead, fender piles, and breasting dolphins.
Additionally, the project will include a concrete roll on roll off (RORO) ramp, fill, armor rock mooring fenders, bullrail, bollards, and cleats.
Activities to be Performed
The HMIC cargo dock will consist of approximately 330 linear feet of sheet pile adjacent to and within the footprint of the existing gravel barge landing.
Approximately 542 sheet piles will make up an open cell structure and approximately 21,160 square feet (SF) and 23,220 cubic yards (CY) of armor rock, shot rock surfacing course, and concrete fill will be placed to make up the cargo dock.
The cargo dock will also include the installation of a barge RORO ramp on the dock deck, five fender piles, and three breasting dolphins—one southeast of the dock and two northwest of the dock.
The scope of work is broken up into the following elements under one component:
Element 1: Project Administration, Contract Administration, Environmental Permitting, Fabrication, and Construction Inspection Services.
Element 2: Construction of Marine Industrial Center Harbor Project, Construction Survey, Contractor Mobilization and Demobilization, Mine Uplands Fill Material Source, Stabilize Cut Area and Create Required Drainage, Sheet Pile Bulkhead Dock and RORO Ramp Install, approximately 330 linear feet of sheet pile to create the open cell structure, place and compact approximately 23,220 CY of engineering fill material behind the sheet piles, construct a 40 by 75 RORO barge ramp, breasting and mooring improvements, bulkhead fender assembly, bulkhead mooring bollards and cleats, ramp mooring bollards, bullrail and cleats, installation of 5 fender dolphins, installation of 3 barge breasting dolphins, lighting utility installation.
Deliverables
Expected outcomes, performance measures as outlined in the grant agreement, page 11, schedule H.
Measure Maritime.
Category and Description: Vessel Calls Measures the number of vessels calling to the project study area per year.
Must be reported in total and disaggregated by any of the following where applicable: vessel type (e.g., container, bulk, RORO, LNG), freight capacity, vessel length, or other.
Measurement frequency: Quarterly.
Measure Maritime.
Category and Description: Vessel Turn Time, average vessel turn time (hours), meaning the time between a vessel first reporting at the port to the time it departs, including berth waiting time and servicing time.
Measurement frequency: Quarterly.
Intended Beneficiary: City of Hoonah.
Subrecipient Activities: None.
Awardee
Funding Goals
ASSIST IN FUNDING ELIGIBLE PROJECTS FOR THE PURPOSE OF IMPROVING THE SAFETY EFFICIENCY OR RELIABILITY OF THE MOVEMENT OF GOODS THROUGH PORTS AND INTERMODAL CONNECTIONS TO PORTS.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Hoonah,
Alaska
99829-0360
United States
Geographic Scope
Single Zip Code
Related Opportunity
City Of Hoonah was awarded
Marine Industrial Center Harbor Project Grant for City of Hoonah
Project Grant 693JF72540020
worth $9,429,201
from Maritime Administration in December 2025 with work to be completed primarily in Hoonah Alaska United States.
The grant
has a duration of 2 years 2 months and
was awarded through assistance program 20.823 Port Infrastructure Development Program.
$6,081,648 (39.0%) of this Project Grant was funded by non-federal sources.
The Project Grant was awarded through grant opportunity Port Infrastructure Development Program.
Status
(Ongoing)
Last Modified 1/10/26
Period of Performance
12/18/25
Start Date
2/29/28
End Date
Funding Split
$9.4M
Federal Obligation
$6.1M
Non-Federal Obligation
$15.5M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
693JF72540020
SAI Number
None
Award ID URI
SAI NOT APPLICABLE
Awardee Classifications
State Government
Awarding Office
69A334 MARITIME ADMINISTRATION
Funding Office
69A334 MARITIME ADMINISTRATION
Awardee UEI
Y3YJLPAGH699
Awardee CAGE
38VR6
Performance District
AK-00
Senators
Lisa Murkowski
Dan Sullivan
Dan Sullivan
Modified: 1/10/26