693JF72444089
Project Grant
Overview
Grant Description
Award Purpose
The project includes final design and construction of an approximately 200,000 square foot (SF) warehouse along with an associated rail spur extension and terminal roadway improvements to serve the warehouse.
Activities to be performed
The project will be completed in three components with the following elements:
Component 1: Design and engineering, permitting and construction administration, basis of design and data analysis, geotechnical services, survey engineering, design development (0 percent), final phasing analysis, conceptual design and alternative analysis, final permitting (NEPA), environmental assessment, engineering support during construction and review of domestic preference compliance, project inspections as required, coordinate issuance of certificate of occupancy, punch list, and final walkthrough.
Component 2: Phase I construction
Remove existing paving, surcharge the existing site to develop suitable load characteristics, partial rail construction for site workflow including an at-grade rail crossing on the entrance road to the warehouse.
Component 3: Phase II construction
Element 1: Approximately 200,000 SF warehouse.
Warehouse will be a high bay long span pre-engineered metal building with overhead doors, designed to meet the Florida Building Code and Americans with Disabilities Act (ADA) requirements.
Mobilization, ram aggregate piers for building foundations, building foundations, slabs and stem walls, site civil including storm drainage connections, rerouting, final grading and paving both asphalt and concrete for building approaches and access points.
Install building fire loop to the existing fire protection system and tank, install water and sewer services to the existing mains, install new primary loop feed and transformer, connect to the existing stormwater facility, install concrete slab on grade and knee walls including rebar, install dock levelers and warehouse sediment traps, install sub facilities including an office, mechanical room, electrical room, and multiple bathrooms.
Install electrical service and panels to support new warehouse functions utilizing the existing primary electrical feed with a new transformer, install new heating, ventilation, and air conditioning (HVAC) components for the heated and cooled portions of the facility, install communication ducts to a new communication room.
Element 2: Rail spur
Remove existing rail as required to establish crossover, install new concrete grade crossing, extend the existing dock rail from east of the crossing with 115, 132, 136 American Railway Engineering and Maintenance of Way Association (AREM) rail; approximately 1,000 track feet, install two No. 8 turnouts to create a crossover.
Element 3: Terminal roadway improvements
Install road patch for stormwater crossing, install road patch for utility connections, install final concrete and asphalt connections to warehouse.
Deliverables
Expected outcomes, performance measures from the grant agreement, page 12, schedule G.
Intended beneficiary: Panama City Port Authority.
Subrecipient activities: None.
The project includes final design and construction of an approximately 200,000 square foot (SF) warehouse along with an associated rail spur extension and terminal roadway improvements to serve the warehouse.
Activities to be performed
The project will be completed in three components with the following elements:
Component 1: Design and engineering, permitting and construction administration, basis of design and data analysis, geotechnical services, survey engineering, design development (0 percent), final phasing analysis, conceptual design and alternative analysis, final permitting (NEPA), environmental assessment, engineering support during construction and review of domestic preference compliance, project inspections as required, coordinate issuance of certificate of occupancy, punch list, and final walkthrough.
Component 2: Phase I construction
Remove existing paving, surcharge the existing site to develop suitable load characteristics, partial rail construction for site workflow including an at-grade rail crossing on the entrance road to the warehouse.
Component 3: Phase II construction
Element 1: Approximately 200,000 SF warehouse.
Warehouse will be a high bay long span pre-engineered metal building with overhead doors, designed to meet the Florida Building Code and Americans with Disabilities Act (ADA) requirements.
Mobilization, ram aggregate piers for building foundations, building foundations, slabs and stem walls, site civil including storm drainage connections, rerouting, final grading and paving both asphalt and concrete for building approaches and access points.
Install building fire loop to the existing fire protection system and tank, install water and sewer services to the existing mains, install new primary loop feed and transformer, connect to the existing stormwater facility, install concrete slab on grade and knee walls including rebar, install dock levelers and warehouse sediment traps, install sub facilities including an office, mechanical room, electrical room, and multiple bathrooms.
Install electrical service and panels to support new warehouse functions utilizing the existing primary electrical feed with a new transformer, install new heating, ventilation, and air conditioning (HVAC) components for the heated and cooled portions of the facility, install communication ducts to a new communication room.
Element 2: Rail spur
Remove existing rail as required to establish crossover, install new concrete grade crossing, extend the existing dock rail from east of the crossing with 115, 132, 136 American Railway Engineering and Maintenance of Way Association (AREM) rail; approximately 1,000 track feet, install two No. 8 turnouts to create a crossover.
Element 3: Terminal roadway improvements
Install road patch for stormwater crossing, install road patch for utility connections, install final concrete and asphalt connections to warehouse.
Deliverables
Expected outcomes, performance measures from the grant agreement, page 12, schedule G.
Intended beneficiary: Panama City Port Authority.
Subrecipient activities: None.
Awardee
Funding Goals
ASSIST IN FUNDING ELIGIBLE PROJECTS FOR THE PURPOSE OF IMPROVING THE SAFETY EFFICIENCY OR RELIABILITY OF THE MOVEMENT OF GOODS THROUGH PORTS AND INTERMODAL CONNECTIONS TO PORTS.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Panama City,
Florida
32401-1009
United States
Geographic Scope
Single Zip Code
Related Opportunity
Panama City Port Authority was awarded
Florida Warehouse Construction Grant for Panama City Port Authority
Project Grant 693JF72444089
worth $11,250,000
from Maritime Administration in January 2026 with work to be completed primarily in Panama City Florida United States.
The grant
has a duration of 4 years 3 months and
was awarded through assistance program 20.823 Port Infrastructure Development Program.
$17,468,075 (61.0%) of this Project Grant was funded by non-federal sources.
The Project Grant was awarded through grant opportunity 2023 Port Infrastructure Development Program Grants.
Status
(Ongoing)
Last Modified 1/22/26
Period of Performance
1/16/26
Start Date
4/30/30
End Date
Funding Split
$11.2M
Federal Obligation
$17.5M
Non-Federal Obligation
$28.7M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
693JF72444089
SAI Number
None
Award ID URI
SAI NOT APPLICABLE
Awardee Classifications
State Government
Awarding Office
69A334 MARITIME ADMINISTRATION
Funding Office
69A334 MARITIME ADMINISTRATION
Awardee UEI
PTTMJ8JVTCB9
Awardee CAGE
1PA23
Performance District
FL-02
Senators
Marco Rubio
Rick Scott
Rick Scott
Modified: 1/22/26