693JF72444078
Project Grant
Overview
Grant Description
Award purpose
The project will replace a conveyor system at the Inland River Port.
Project elements include a new roughly 1200 foot long conveyor system, foundations for the conveyor, new mooring cell, electrical infrastructure, and control mechanisms.
The project also includes environmental engineering, construction administration, testing and inspection, and procurement services.
Activities to be performed
The project scope of work includes one component with the following elements: new roughly 1200 ft conveyor system with a 48 inch belt, 100HP DODGE drive package, conveyor foundations, new 24 ft diameter mooring cell, electrical infrastructure, remote control technology to include wireless multi switch controller, environmental professional engineering design services, construction administration and testing and inspection services, and procurement services.
Deliverables
Expected outcomes from Schedule G page 10 of the grant agreement measure vessel calls.
Category and description
Measures the number of vessels calling to the project study area.
Must be reported in total and disaggregated by any of the following where applicable: vessel type (e.g., container, bulk, RO-RO, LNG), freight capacity, vessel length, or other.
Measurement frequency: quarterly.
Measure cargo volume
Category and description
Measurement cargo volume measures the movement of freight through the project study area.
When applicable, report the total cargo volume and the volume disaggregated by type of freight (i.e., containers in TEU and bulk in tons) or type of intermodal transport (truck or rail).
Frequency: quarterly.
Intended beneficiary
Hickman-Fulton County Riverport Authority Inc.
Subrecipient activities: none.
The project will replace a conveyor system at the Inland River Port.
Project elements include a new roughly 1200 foot long conveyor system, foundations for the conveyor, new mooring cell, electrical infrastructure, and control mechanisms.
The project also includes environmental engineering, construction administration, testing and inspection, and procurement services.
Activities to be performed
The project scope of work includes one component with the following elements: new roughly 1200 ft conveyor system with a 48 inch belt, 100HP DODGE drive package, conveyor foundations, new 24 ft diameter mooring cell, electrical infrastructure, remote control technology to include wireless multi switch controller, environmental professional engineering design services, construction administration and testing and inspection services, and procurement services.
Deliverables
Expected outcomes from Schedule G page 10 of the grant agreement measure vessel calls.
Category and description
Measures the number of vessels calling to the project study area.
Must be reported in total and disaggregated by any of the following where applicable: vessel type (e.g., container, bulk, RO-RO, LNG), freight capacity, vessel length, or other.
Measurement frequency: quarterly.
Measure cargo volume
Category and description
Measurement cargo volume measures the movement of freight through the project study area.
When applicable, report the total cargo volume and the volume disaggregated by type of freight (i.e., containers in TEU and bulk in tons) or type of intermodal transport (truck or rail).
Frequency: quarterly.
Intended beneficiary
Hickman-Fulton County Riverport Authority Inc.
Subrecipient activities: none.
Funding Goals
ASSIST IN FUNDING ELIGIBLE PROJECTS FOR THE PURPOSE OF IMPROVING THE SAFETY EFFICIENCY OR RELIABILITY OF THE MOVEMENT OF GOODS THROUGH PORTS AND INTERMODAL CONNECTIONS TO PORTS.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Hickman,
Kentucky
42050-1124
United States
Geographic Scope
Single Zip Code
Related Opportunity
Hickman-Fulton County Riverport Authority was awarded
Inland River Port Conveyor System Replacement Grant
Project Grant 693JF72444078
worth $3,295,879
from Maritime Administration in March 2026 with work to be completed primarily in Hickman Kentucky United States.
The grant
has a duration of 2 years 6 months and
was awarded through assistance program 20.823 Port Infrastructure Development Program.
$823,970 (20.0%) of this Project Grant was funded by non-federal sources.
The Project Grant was awarded through grant opportunity 2023 Port Infrastructure Development Program Grants.
Status
(Ongoing)
Last Modified 3/9/26
Period of Performance
3/4/26
Start Date
9/27/28
End Date
Funding Split
$3.3M
Federal Obligation
$824.0K
Non-Federal Obligation
$4.1M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
693JF72444078
SAI Number
None
Award ID URI
SAI NOT APPLICABLE
Awardee Classifications
For-Profit Organization (Other Than Small Business)
Awarding Office
69A334 MARITIME ADMINISTRATION
Funding Office
69A334 MARITIME ADMINISTRATION
Awardee UEI
NEPJP1KCJZK1
Awardee CAGE
59D12
Performance District
KY-01
Senators
Mitch McConnell
Rand Paul
Rand Paul
Modified: 3/9/26