Grant Description
Award Purpose
The project consists of installing more than 1000 feet of new floating dock and supporting access utility and safety infrastructure within the existing harbor.
The project will complete the Aleutians East Borough's long-term efforts to fully build out the community's harbor.
Activities to be performed
The project consists of installing more than 1000 feet of new floating dock and supporting access utility and safety infrastructure within the existing harbor.
The floating dock consists of installing a new prefabricated treated timber floating dock within the existing harbor in addition to in-water and upland improvements.
The project includes furnishing and installing the floats, trestle, gangway, and landing float, furnishing and driving steel piles, installing potable water systems, and installing fire protection, electrical lighting, cathodic protection, and other safety systems.
Constructing the floating dock will bring the facility to full utilization and double its capacity, increasing moorage space in the harbor from 254 lineal feet (LF) to roughly 1308 LF for vessels of all sizes.
The project consists of two components.
Component 1: Construction management
All activities to review bids and award the construction contract and contractor procurement and submittals.
Construction phase services, technical support during construction, and construction contract closeout activities (e.g., responding to RFIs, verifying as-constructed red line drawings, etc.).
All project closeout activities.
Component 2: Sand Point floating dock installation and construction
Installation of a float system referred to as FLOAT A, which will be prefabricated and Americans with Disabilities (ADA) compliant for vessel moorage.
The float will consist of individual float sections.
Materials include treated timber decking and plastic flotation material connected into a single system.
The float system will be about 12 feet (FT) wide and about 1054 LF long.
The float system will be secured with up to 92 new galvanized steel pipe piles up to 24 inches in diameter or less, including all piles to also support access trestle and gangway.
Installation of three prefabricated transformer floats about 12 FT long by 6 FT wide to support the electrical system upgrades for the main float.
Installation of a prefabricated aluminum gangway about 80 FT long by 6 FT wide for float access.
Installation of a new prefabricated ADA compliant gangway landing float about 20 FT long and 20 FT wide for float access, secured by up to two new galvanized steel pipe piles 24 inches in diameter or less to stabilize the float.
Construction of a treated timber decked steel pile supported access trestle from the top of the existing harbor bulkhead wall to the gangway.
The trestle deck will be 30 FT long by 20 FT wide.
Up to 15 cubic yards (CY) of existing rock rip rap along the shoreline may need to be moved to the side, reworked, and possibly replaced (with up to 5 CY of clean rock) once the trestle support piles have been installed.
Approximately 20 CY of fill will be placed in the uplands above the high tide line (HTL) to grade the approach to the new trestle.
Power and lighting cables will run from the new access trestle down the gangway and into the float system's utility chaseways.
The new power lines will daylight from the shoreline slope at an elevation of 4 FT mean lower low water (MLLW).
Up to two concrete anchor blocks 2 FT by 2 FT by 2 FT in size will hold the lines in place at this daylight location.
Potable water and fire protection lines will run from the existing power and water connections located on the uplands adjacent to the proposed new access trestle through a 6 FT deep (average 4 FT wide) trench to the shoreline.
The trench for the water and fire protection line is anticipated to displace up to 20 CY of fill material and 7 CY of armor rock below HTL.
The potable water and dry standpipe fire protection systems will submerge approximately 1100 LF of 3 inch and 4 inch high-density polyethylene (HDPE) pipe and 60 LF of 3 inch and 4 inch flexible hose below mean higher high water (MHHW).
Flexible hoses will connect the buried lines to the floating docks.
Chains may be used to weigh down the lines so that they remain submerged until they connect to the float system.
Deliverables
Expected outcomes
Performance measure table from Schedule G, page 10 of the grant agreement
Measure category and description
Reportable events
Safety
Quality of life
Total number of reportable events per year.
Annual vessel calls
Economic competitiveness
Vessel type and/or freight capacity of the vessels calling to the area defined in the project study area.
Quarterly intended beneficiary: Aleutians East Borough.
Subrecipient activities: None.
The project consists of installing more than 1000 feet of new floating dock and supporting access utility and safety infrastructure within the existing harbor.
The project will complete the Aleutians East Borough's long-term efforts to fully build out the community's harbor.
Activities to be performed
The project consists of installing more than 1000 feet of new floating dock and supporting access utility and safety infrastructure within the existing harbor.
The floating dock consists of installing a new prefabricated treated timber floating dock within the existing harbor in addition to in-water and upland improvements.
The project includes furnishing and installing the floats, trestle, gangway, and landing float, furnishing and driving steel piles, installing potable water systems, and installing fire protection, electrical lighting, cathodic protection, and other safety systems.
Constructing the floating dock will bring the facility to full utilization and double its capacity, increasing moorage space in the harbor from 254 lineal feet (LF) to roughly 1308 LF for vessels of all sizes.
The project consists of two components.
Component 1: Construction management
All activities to review bids and award the construction contract and contractor procurement and submittals.
Construction phase services, technical support during construction, and construction contract closeout activities (e.g., responding to RFIs, verifying as-constructed red line drawings, etc.).
All project closeout activities.
Component 2: Sand Point floating dock installation and construction
Installation of a float system referred to as FLOAT A, which will be prefabricated and Americans with Disabilities (ADA) compliant for vessel moorage.
The float will consist of individual float sections.
Materials include treated timber decking and plastic flotation material connected into a single system.
The float system will be about 12 feet (FT) wide and about 1054 LF long.
The float system will be secured with up to 92 new galvanized steel pipe piles up to 24 inches in diameter or less, including all piles to also support access trestle and gangway.
Installation of three prefabricated transformer floats about 12 FT long by 6 FT wide to support the electrical system upgrades for the main float.
Installation of a prefabricated aluminum gangway about 80 FT long by 6 FT wide for float access.
Installation of a new prefabricated ADA compliant gangway landing float about 20 FT long and 20 FT wide for float access, secured by up to two new galvanized steel pipe piles 24 inches in diameter or less to stabilize the float.
Construction of a treated timber decked steel pile supported access trestle from the top of the existing harbor bulkhead wall to the gangway.
The trestle deck will be 30 FT long by 20 FT wide.
Up to 15 cubic yards (CY) of existing rock rip rap along the shoreline may need to be moved to the side, reworked, and possibly replaced (with up to 5 CY of clean rock) once the trestle support piles have been installed.
Approximately 20 CY of fill will be placed in the uplands above the high tide line (HTL) to grade the approach to the new trestle.
Power and lighting cables will run from the new access trestle down the gangway and into the float system's utility chaseways.
The new power lines will daylight from the shoreline slope at an elevation of 4 FT mean lower low water (MLLW).
Up to two concrete anchor blocks 2 FT by 2 FT by 2 FT in size will hold the lines in place at this daylight location.
Potable water and fire protection lines will run from the existing power and water connections located on the uplands adjacent to the proposed new access trestle through a 6 FT deep (average 4 FT wide) trench to the shoreline.
The trench for the water and fire protection line is anticipated to displace up to 20 CY of fill material and 7 CY of armor rock below HTL.
The potable water and dry standpipe fire protection systems will submerge approximately 1100 LF of 3 inch and 4 inch high-density polyethylene (HDPE) pipe and 60 LF of 3 inch and 4 inch flexible hose below mean higher high water (MHHW).
Flexible hoses will connect the buried lines to the floating docks.
Chains may be used to weigh down the lines so that they remain submerged until they connect to the float system.
Deliverables
Expected outcomes
Performance measure table from Schedule G, page 10 of the grant agreement
Measure category and description
Reportable events
Safety
Quality of life
Total number of reportable events per year.
Annual vessel calls
Economic competitiveness
Vessel type and/or freight capacity of the vessels calling to the area defined in the project study area.
Quarterly intended beneficiary: Aleutians East Borough.
Subrecipient activities: None.
Awardee
Funding Goals
ASSIST IN FUNDING ELIGIBLE PROJECTS FOR THE PURPOSE OF IMPROVING THE SAFETY EFFICIENCY OR RELIABILITY OF THE MOVEMENT OF GOODS THROUGH PORTS AND INTERMODAL CONNECTIONS TO PORTS.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Anchorage,
Alaska
99503-3952
United States
Geographic Scope
Single Zip Code
Related Opportunity
MAPID22001
Aleutians East Borough was awarded
Harbor Expansion Project: Floating Dock Installation
Project Grant 693JF72344015
worth $5,365,000
from Maritime Administration in September 2024 with work to be completed primarily in Anchorage Alaska United States.
The grant
has a duration of 5 years 1 months and
was awarded through assistance program 20.823 Port Infrastructure Development Program.
$4,125,000 (43.0%) of this Project Grant was funded by non-federal sources.
Status
(Ongoing)
Last Modified 9/13/24
Period of Performance
9/6/24
Start Date
10/31/29
End Date
Funding Split
$5.4M
Federal Obligation
$4.1M
Non-Federal Obligation
$9.5M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
693JF72344015
SAI Number
None
Award ID URI
SAI NOT APPLICABLE
Awardee Classifications
State Government
Awarding Office
69A334 MARITIME ADMINISTRATION
Funding Office
69A334 MARITIME ADMINISTRATION
Awardee UEI
R1T5FLNFFEP4
Awardee CAGE
4JZT6
Performance District
AK-00
Senators
Lisa Murkowski
Dan Sullivan
Dan Sullivan
Modified: 9/13/24