The project will construct a four lane rail roadway grade separation that will eliminate a significant truck access impediment to an important container terminal support facility located on Terminal Island at the centroid of the Port of Los Angeles Long Beach (POLA) (POLB).
Activities to be performed
The project will construct a four lane grade separated roadway over the Port of Los Angeles mainline rail tracks connecting Terminal Way, Ferry Street, and Pier 300 to the Terminal Island maritime support facility without impeded access and includes the following activities:
Site work, site preparation of approximately 7 acres including clearing, grubbing, and grading - utility removals, relocations, site excavation, construction of retaining walls, construction of a grade separation roadway structure of approximately 2000 feet, intersection modifications including traffic signal and street lighting improvements, paving and striping, storm drain improvements, landscaping, construction management, architectural and engineering.
Deliverables expected outcomes
Performance measure table from schedule G page 10 of the grant agreement:
Measure category and description, measurement frequency
Rail track grade separation economic competitiveness safety: The number of automobile crossings that are eliminated at an at-grade crossing as a result of a new grade separation. Quarterly.
Severe crashes safety: Total severe crashes per year. Quarterly.
Intended beneficiary: Los Angeles City of subrecipient activities none.
The project will construct a four lane rail roadway grade separation that will eliminate a significant truck access impediment to an important container terminal support facility located on Terminal Island at the centroid of the Port of Los Angeles Long Beach (POLA) (POLB).
Activities to be performed
The project will construct a four lane grade separated roadway over the Port of Los Angeles mainline rail tracks connecting Terminal Way, Ferry Street, and Pier 300 to the Terminal Island maritime support facility without impeded access and includes the following activities:
Site work, site preparation of approximately 7 acres including clearing, grubbing, and grading - utility removals, relocations, site excavation, construction of retaining walls, construction of a grade separation roadway structure of approximately 2000 feet, intersection modifications including traffic signal and street lighting improvements, paving and striping, storm drain improvements, landscaping, construction management, architectural and engineering.
Deliverables expected outcomes
Performance measure table from schedule G page 10 of the grant agreement:
Measure category and description, measurement frequency
Rail track grade separation economic competitiveness safety: The number of automobile crossings that are eliminated at an at-grade crossing as a result of a new grade separation. Quarterly.
Severe crashes safety: Total severe crashes per year. Quarterly.
Intended beneficiary: Los Angeles City of subrecipient activities none.
Awardee
Funding Goals
THE RAISE PROGRAM INVESTS IN SURFACE TRANSPORTATION PROJECTS THAT WILL HAVE SIGNIFICANT LOCAL OR REGIONAL IMPACT AND IMPROVE SAFETY ECONOMIC STRENGTH AND GLOBAL COMPETITIVENESS EQUITY AND CLIMATE AND SUSTAINABILITY.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
San Pedro,
California
90731-3309
United States
Geographic Scope
Single Zip Code
Related Opportunity
City Of Los Angeles was awarded
Port of Los Angeles Railroad Grade Separation Project
Project Grant 693JF72340016
worth $20,000,000
from Maritime Administration in September 2024 with work to be completed primarily in San Pedro California United States.
The grant
has a duration of 7 years 6 months and
was awarded through assistance program 20.933 National Infrastructure Investments.
$19,277,624 (49.0%) of this Project Grant was funded by non-federal sources.
The Project Grant was awarded through grant opportunity FY 2022 National Infrastructure Investments.
Status
(Ongoing)
Last Modified 9/27/24
Period of Performance
9/20/24
Start Date
3/31/32
End Date
Funding Split
$20.0M
Federal Obligation
$19.3M
Non-Federal Obligation
$39.3M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
693JF72340016
SAI Number
None
Award ID URI
SAI NOT APPLICABLE
Awardee Classifications
State Government
Awarding Office
69A334 MARITIME ADMINISTRATION
Funding Office
69A334 MARITIME ADMINISTRATION
Awardee UEI
TYUJZWJ8N568
Awardee CAGE
4GJK6
Performance District
CA-44
Senators
Dianne Feinstein
Alejandro Padilla
Alejandro Padilla
Modified: 9/27/24