The project consists of developing approximately 50 acres of container yard at the Bayport Container Terminal.
The construction includes but is not limited to container yard grading and drainage utilities, power, roller compacted concrete (RCC), and/or other types of concrete pavement used in the storage of containerized cargo and other components required for upgrade.
Activities to be performed
Component 1: Electrical unit substation
Purchase of long lead time 1000 KVA electrical unit substation.
Component 2: Construction of container yard
Mobilization, site preparation, and excavation including but not limited to removal of existing pavement and structures.
Earthwork utility items including but not limited to waterlines, 8 inches DIP distribution line roughly 1151 linear feet (LF), potable water stations, 6 electrical vacuum breakers, 6 BDP 600 breakers, 2 500 KCMIL MV, 5 inches conduit roughly 16690 LF, 2 inches conduit roughly 17870 LF, lift station feeder tie switch, communications, various size of single mode fiber roughly 13415 LF, splice closures, 8 fiber termination and termination equipment.
Concrete including but not limited to concrete formwork, concrete joints and incidentals, cast in place concrete, structural concrete, pre-stressed concrete poles, concrete submittals and testing.
Specialty items including but not limited to metal concrete filled steel bollard with paintings and markings finishes, drilled shaft foundation for high mast light pole, and drilled and underreamed footings for RTG tie downs.
Exterior improvement
RCC joint reinforced concrete and pavement markings and signage.
Building items including but not limited to exterior improvements, 18 inches joint reinforced concrete pavement roughly 10000 square yards (SY), 18 inches approach slab with sleeper slab roughly 2500 SY.
Precast building
Building foundation and approach slab, building erection roughly 2500 square feet (SF).
Deliverables
Expected outcomes performance measure table from Attachment C, page 9 of the grant agreement.
Measure category and description of measure
Freight movements.
Economic competitiveness total freight movements measured in TEUs categorized by inbound freight movements and outbound freight movements.
Truck turn time.
Environmental impacts and economic competitiveness.
Truck turn time captured by average minutes.
This is the arrival gate to exit gate time gross tons economic competitiveness short tons.
Information is stored in the recipient's billing software and checked against operational data.
The information is provided monthly in the recipient's tonnage report.
Tonnage and TEUs are tracked individually.
Intended beneficiary
Port of Houston Authority.
Subrecipient activities
None.
The project consists of developing approximately 50 acres of container yard at the Bayport Container Terminal.
The construction includes but is not limited to container yard grading and drainage utilities, power, roller compacted concrete (RCC), and/or other types of concrete pavement used in the storage of containerized cargo and other components required for upgrade.
Activities to be performed
Component 1: Electrical unit substation
Purchase of long lead time 1000 KVA electrical unit substation.
Component 2: Construction of container yard
Mobilization, site preparation, and excavation including but not limited to removal of existing pavement and structures.
Earthwork utility items including but not limited to waterlines, 8 inches DIP distribution line roughly 1151 linear feet (LF), potable water stations, 6 electrical vacuum breakers, 6 BDP 600 breakers, 2 500 KCMIL MV, 5 inches conduit roughly 16690 LF, 2 inches conduit roughly 17870 LF, lift station feeder tie switch, communications, various size of single mode fiber roughly 13415 LF, splice closures, 8 fiber termination and termination equipment.
Concrete including but not limited to concrete formwork, concrete joints and incidentals, cast in place concrete, structural concrete, pre-stressed concrete poles, concrete submittals and testing.
Specialty items including but not limited to metal concrete filled steel bollard with paintings and markings finishes, drilled shaft foundation for high mast light pole, and drilled and underreamed footings for RTG tie downs.
Exterior improvement
RCC joint reinforced concrete and pavement markings and signage.
Building items including but not limited to exterior improvements, 18 inches joint reinforced concrete pavement roughly 10000 square yards (SY), 18 inches approach slab with sleeper slab roughly 2500 SY.
Precast building
Building foundation and approach slab, building erection roughly 2500 square feet (SF).
Deliverables
Expected outcomes performance measure table from Attachment C, page 9 of the grant agreement.
Measure category and description of measure
Freight movements.
Economic competitiveness total freight movements measured in TEUs categorized by inbound freight movements and outbound freight movements.
Truck turn time.
Environmental impacts and economic competitiveness.
Truck turn time captured by average minutes.
This is the arrival gate to exit gate time gross tons economic competitiveness short tons.
Information is stored in the recipient's billing software and checked against operational data.
The information is provided monthly in the recipient's tonnage report.
Tonnage and TEUs are tracked individually.
Intended beneficiary
Port of Houston Authority.
Subrecipient activities
None.
Awardee
Funding Goals
ASSIST IN FUNDING ELIGIBLE PROJECTS FOR THE PURPOSE OF IMPROVING THE SAFETY EFFICIENCY OR RELIABILITY OF THE MOVEMENT OF GOODS THROUGH PORTS AND INTERMODAL CONNECTIONS TO PORTS.
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Houston,
Texas
77029-4326
United States
Geographic Scope
Single Zip Code
Related Opportunity
MAPID21001
Port Of Houston Authority was awarded
Container Yard Development Grant for Port of Houston Authority
Project Grant 693JF72245032
worth $18,267,600
from Maritime Administration in September 2024 with work to be completed primarily in Houston Texas United States.
The grant
has a duration of 5 years 4 months and
was awarded through assistance program 20.823 Port Infrastructure Development Program.
$80,269,331 (81.0%) of this Project Grant was funded by non-federal sources.
Status
(Ongoing)
Last Modified 9/30/24
Period of Performance
9/26/24
Start Date
1/31/30
End Date
Funding Split
$18.3M
Federal Obligation
$80.3M
Non-Federal Obligation
$98.5M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
693JF72245032
SAI Number
None
Award ID URI
SAI NOT APPLICABLE
Awardee Classifications
State Government
Awarding Office
69A334 MARITIME ADMINISTRATION
Funding Office
69A334 MARITIME ADMINISTRATION
Awardee UEI
JNGVKR5UVAM5
Awardee CAGE
1EKW0
Performance District
TX-18
Senators
John Cornyn
Ted Cruz
Ted Cruz
Modified: 9/30/24