Description: This agreement provides funding to City of Waukegan, IL to implement its water works improvement project as directed in the 2023 Consolidated Appropriations Act or as identified in an approved technical correction if one has been approved for this project.
Activities: The activities to be performed include the execution and implementation of a drinking water infrastructure construction project.
Workplan activities consist of water treatment plant improvements.
Subrecipient: No subawards are included in this assistance agreement.
Outcomes: The anticipated deliverables include the replacement of the existing programmable logic controllers (PLCs) with the Allen-Bradley ControlLogix series, as well as replace the existing legacy remote I/O (RIO) PLC network communications with Ethernet.
Additional deliverables include replacing the 4,160-volt switchgear and 480-volt motor control centers (MCC) equipment located in the high service pump room.
The expected outcomes include improved functionality and reliability for the city's water filtration plant (WFP).
The SCADA/PLC and MCC systems are outdated and beyond their serviceable life or are altogether obsolete.
These upgrades are critical for the continued operation and reliability for the WFP.
The intended beneficiaries include the residents of the City of Waukegan.
Activities: The activities to be performed include the execution and implementation of a drinking water infrastructure construction project.
Workplan activities consist of water treatment plant improvements.
Subrecipient: No subawards are included in this assistance agreement.
Outcomes: The anticipated deliverables include the replacement of the existing programmable logic controllers (PLCs) with the Allen-Bradley ControlLogix series, as well as replace the existing legacy remote I/O (RIO) PLC network communications with Ethernet.
Additional deliverables include replacing the 4,160-volt switchgear and 480-volt motor control centers (MCC) equipment located in the high service pump room.
The expected outcomes include improved functionality and reliability for the city's water filtration plant (WFP).
The SCADA/PLC and MCC systems are outdated and beyond their serviceable life or are altogether obsolete.
These upgrades are critical for the continued operation and reliability for the WFP.
The intended beneficiaries include the residents of the City of Waukegan.
Awardee
Funding Goals
1 - PILLAR 1: CLEAN AIR, LAND, AND WATER FOR EVERY AMERICAN 1.1 - TBD
Grant Program (CFDA)
Awarding / Funding Agency
Place of Performance
Waukegan,
Illinois
United States
Geographic Scope
City-Wide
Related Opportunity
EPA-CEP-01
Waukegan, City Of was awarded
Water Works Improvement Grant for City of Waukegan, IL
Cooperative Agreement 00E06073
worth $3,452,972
from EPA Region 5: Chicago in February 2024 with work to be completed primarily in Waukegan Illinois United States.
The grant
has a duration of 3 years 6 months and
was awarded through assistance program 66.202 Congressionally Mandated Projects.
Status
(Ongoing)
Last Modified 10/6/25
Period of Performance
2/1/24
Start Date
8/5/27
End Date
Funding Split
$3.5M
Federal Obligation
$0.0
Non-Federal Obligation
$3.5M
Total Obligated
Activity Timeline
Additional Detail
Award ID FAIN
00E06073
SAI Number
None
Award ID URI
SAI EXEMPT
Awardee Classifications
City Or Township Government
Awarding Office
68HF05 REGION 5 (GRANTS OFFICE)
Funding Office
68U000 REGION 5 (FUNDING OFFICE)
Awardee UEI
EH3LGGUCQ727
Awardee CAGE
3PPM9
Performance District
IL-10
Senators
Richard Durbin
Tammy Duckworth
Tammy Duckworth
Modified: 10/6/25