P01 - SOW Exhibit A-Annotated Drawings - 537-26-200 ADDENDUM 1.pdf
Posted: June 4, 2026
• Type: .pdf
• Size: 12.51MB
Submit Questions to Government Officer Anonymously
Place your question(s) below. One of our analysts will anonymously submit the question(s) within 8 hours and provide any responses via email once received.
Opportunity Assistant
Hello! Please let me know your questions about this document.
Loading
Save a Question
Customize Generation
We will write a draft based on the below linked information. Add or link more information to improve the draft.
Federal Profile
Select the Federal company profile to use when informing the response based on publicly available data.
Loading federal profile search...
Company Context
Add capability statements, prior responses, or other company materials to customize the response to your business.
Checking for company documents...
Opportunity Context
Add SOWs, attachments, or other files specific to this opportunity.
Checking for opportunity documents...
Link a Pursuit
Optionally associate this draft with an existing pursuit.
Overview
Related Opportunity
Related Agency
Summary
This Statement of Work (SOW) is for the replacement of the Air Handling Unit (AHU-AC21) serving Nutrition Food and Service at the Jesse Brown Veterans Affairs Medical Center, located in Chicago, Illinois.
The project, identified as 537-26-200, outlines the specific tasks required for the demolition and installation of HVAC systems on the third floor of Building 1-B. Key components of the work include replacing two-pipe fan coil units, kitchen exhaust fans, and a supply air handler, as well as necessary ductwork modifications. The contractor is responsible for all labor, materials, equipment, and services to complete the project in accordance with VA policies and applicable codes.
The SOW emphasizes compliance with various standards including the VA HVAC Design Manual and ASHRAE guidelines. Contractors must submit a demolition plan for approval prior to commencing work and are required to verify existing conditions at the job site.
They must also ensure that all work is performed without disrupting existing utilities servicing occupied areas unless prior written approval is obtained. Additionally, contractors are tasked with maintaining cleanliness throughout construction and are responsible for any damages incurred during their operations.
All work must be completed to the satisfaction of the Jesse Brown VA Medical Center and in accordance with federal, state, and local regulations.
The project, identified as 537-26-200, outlines the specific tasks required for the demolition and installation of HVAC systems on the third floor of Building 1-B. Key components of the work include replacing two-pipe fan coil units, kitchen exhaust fans, and a supply air handler, as well as necessary ductwork modifications. The contractor is responsible for all labor, materials, equipment, and services to complete the project in accordance with VA policies and applicable codes.
The SOW emphasizes compliance with various standards including the VA HVAC Design Manual and ASHRAE guidelines. Contractors must submit a demolition plan for approval prior to commencing work and are required to verify existing conditions at the job site.
They must also ensure that all work is performed without disrupting existing utilities servicing occupied areas unless prior written approval is obtained. Additionally, contractors are tasked with maintaining cleanliness throughout construction and are responsible for any damages incurred during their operations.
All work must be completed to the satisfaction of the Jesse Brown VA Medical Center and in accordance with federal, state, and local regulations.