Search Documents
Construction Industry Day Overview Presentation Slides.pdf
Posted: May 24, 2022
• Type: .pdf
• Size: 1.71MB
Submit Questions to Government Officer Anonymously
Place your question(s) below. One of our analysts will anonymously submit the question(s) within 8 hours and provide any responses via email once received.
Question & Answer Assistant
Hello! Please let me know your question about this document. I will answer based on the related documents for this opportunity.
Some suggestions:
I'd like to anonymously submit a question to the procurement officer(s)
Loading
Overview
Related Opportunity
Related Agency
Summary
Construction Industry Day Overview Presentation for the Upper Ohio Navigation Project. The project team includes Maggie Bernard, Corry Morgan as the lead engineer, and Chris Dening as the project manager. The project involves significant commerce shipping through the Upper Ohio, primarily coal, with other commodities such as petroleum, aggregates, chemicals, ores/minerals, and iron/steel. The project aims to replace existing auxiliary chambers with new main chambers at Montgomery, Emsworth, and Dashields locks.
The Upper Ohio Navigation Project has a current estimated cost of $2.3 billion and a proposed acquisition method of best value trade-off with set-aside for full and open with 10% HUBZone preference. The construction timeline spans from 2024 to 2044 with critical milestones including contract awards for various construction phases.
Contractors have the opportunity to meet one-on-one with USACE on June 8th and 9th, 2022 either in person or via Webex. Security requirements include providing information for criminal history checks by May 25th, 2022, and personal protective equipment (PPE) such as steel-toed boots, hard hats, and life jackets are mandatory at the active construction site of Montgomery Lock.
Feedback questionnaires are requested to be submitted by June 17th.
The Upper Ohio Navigation Project has a current estimated cost of $2.3 billion and a proposed acquisition method of best value trade-off with set-aside for full and open with 10% HUBZone preference. The construction timeline spans from 2024 to 2044 with critical milestones including contract awards for various construction phases.
Contractors have the opportunity to meet one-on-one with USACE on June 8th and 9th, 2022 either in person or via Webex. Security requirements include providing information for criminal history checks by May 25th, 2022, and personal protective equipment (PPE) such as steel-toed boots, hard hats, and life jackets are mandatory at the active construction site of Montgomery Lock.
Feedback questionnaires are requested to be submitted by June 17th.