Search Documents
No Results Found.
No Results Found.
C04 Fire Plan.pdf
Posted: Oct. 7, 2026
• Type: .pdf
• Size: 0.27MB
Submit Questions to Government Officer Anonymously
Place your question(s) below. One of our analysts will anonymously submit the question(s) within 8 hours and provide any responses via email once received.
Opportunity Assistant
Hello! Please let me know your questions about this document.
Loading
Save a Question
Customize Generation
We will write a draft based on the below linked information. Add or link more information to improve the draft.
Federal Profile
Select the Federal company profile to use when informing the response based on publicly available data.
Loading federal profile search...
Company Context
Add capability statements, prior responses, or other company materials to customize the response to your business.
Checking for company documents...
Opportunity Context
Add SOWs, attachments, or other files specific to this opportunity.
Checking for opportunity documents...
Link a Pursuit
Optionally associate this draft with an existing pursuit.
Overview
Related Opportunity
Related Agency
Summary
This Fire Plan for Construction and Service Contracts, issued under U.S. Forest Service references FSH 6309.32 and 6309.11, establishes contractor fire-prevention, fire-suppression, reporting, equipment, personnel, and work-curtailment requirements for activities conducted within a designated contract area.
The plan applies during the Fire Precautionary Period of April 1 through December 1 and requires the contractor to prevent and extinguish fires caused by operations, maintain compliant equipment, designate a qualified fire supervisor, submit and update key-personnel information, support Forest Service inspections, and comply with applicable California laws, including California Public Resources Code requirements.
Required controls include:
- Approved spark arresters on applicable engines and power saws.
- Specified shovels, axes, extinguishers, headlights, backpacks, and landing fire tools.
- Daily removal of wood dust and debris from mechanized harvesting equipment.
- A water tank truck or trailer with:
- At least 300 gallons of suppression water.
- A tested pump.
- 300 feet of high-pressure hose.
- A compliant shutoff nozzle.
- Fuel for at least two hours.
- Related accessories.
Hot saw operations require additional hose capacity and may trigger more stringent equipment and proximity requirements.
Contractors must:
- Obtain written permits before blasting, burning, air-pollution-related activities, camp or warming fires, and welding or cutting.
- Restrict smoking to approved cleared areas.
- Maintain 10-foot fuel clearances around specified equipment and welding areas.
- Use required blasting watches.
- Remove oily materials and prohibit glass containers.
- Maintain reliable communications.
- Provide a qualified fire patrolperson when Project Activity Level (PAL) B or higher applies.
The Forest Service determines and may revise daily PAL restrictions based on fire conditions, weather, and vegetation. Contractors must obtain the predicted level before beginning work by calling 530-233-8819.
Restrictions are cumulative:
- **PAL B:** Requires patrol coverage after mechanical operations, tank trucks at or near active landings, and specified hot saw response capability.
- **PAL C:** Prohibits blasting from 1:00 p.m. to 8:00 p.m. and generally prohibits hot saw operations from 1:00 p.m. to sunset unless enhanced suppression equipment is available.
- **PAL D:** Limits blasting, welding, cutting, and burning and imposes afternoon patrol requirements for numerous operations.
- **PAL Ev:** Prohibits blasting, welding or cutting, and burning while allowing only specified activities under hourly patrol conditions.
- **PAL E:** Permits a narrower set of hauling, loading, servicing, road, and landing-related activities.
All wildfires must be reported to the Forest Service as soon as possible and no later than 15 minutes after discovery, primarily through the Sierra Interagency Communication Center at 775-883-5995.
The caller must provide their identity, callback number, project and location information, legal description, fire size, spread rate, and wind conditions.
The plan applies during the Fire Precautionary Period of April 1 through December 1 and requires the contractor to prevent and extinguish fires caused by operations, maintain compliant equipment, designate a qualified fire supervisor, submit and update key-personnel information, support Forest Service inspections, and comply with applicable California laws, including California Public Resources Code requirements.
Required controls include:
- Approved spark arresters on applicable engines and power saws.
- Specified shovels, axes, extinguishers, headlights, backpacks, and landing fire tools.
- Daily removal of wood dust and debris from mechanized harvesting equipment.
- A water tank truck or trailer with:
- At least 300 gallons of suppression water.
- A tested pump.
- 300 feet of high-pressure hose.
- A compliant shutoff nozzle.
- Fuel for at least two hours.
- Related accessories.
Hot saw operations require additional hose capacity and may trigger more stringent equipment and proximity requirements.
Contractors must:
- Obtain written permits before blasting, burning, air-pollution-related activities, camp or warming fires, and welding or cutting.
- Restrict smoking to approved cleared areas.
- Maintain 10-foot fuel clearances around specified equipment and welding areas.
- Use required blasting watches.
- Remove oily materials and prohibit glass containers.
- Maintain reliable communications.
- Provide a qualified fire patrolperson when Project Activity Level (PAL) B or higher applies.
The Forest Service determines and may revise daily PAL restrictions based on fire conditions, weather, and vegetation. Contractors must obtain the predicted level before beginning work by calling 530-233-8819.
Restrictions are cumulative:
- **PAL B:** Requires patrol coverage after mechanical operations, tank trucks at or near active landings, and specified hot saw response capability.
- **PAL C:** Prohibits blasting from 1:00 p.m. to 8:00 p.m. and generally prohibits hot saw operations from 1:00 p.m. to sunset unless enhanced suppression equipment is available.
- **PAL D:** Limits blasting, welding, cutting, and burning and imposes afternoon patrol requirements for numerous operations.
- **PAL Ev:** Prohibits blasting, welding or cutting, and burning while allowing only specified activities under hourly patrol conditions.
- **PAL E:** Permits a narrower set of hauling, loading, servicing, road, and landing-related activities.
All wildfires must be reported to the Forest Service as soon as possible and no later than 15 minutes after discovery, primarily through the Sierra Interagency Communication Center at 775-883-5995.
The caller must provide their identity, callback number, project and location information, legal description, fire size, spread rate, and wind conditions.