AOM & AITD Site Visit and
Industry Day Questions &
Answers

August 2nd, 2022

Aviation Institute of Training Division (AITD)

Reference:

Text states that the scope of the requirement
includes AH-64, UH-60, AH-6i, and MD-530F
Maintenance and Pilot Training, Flight and Non-
Flight Aircrew Training, and the build-up for
Airfield Operations and Support.

Question: Please describe to what extent
aircraft maintenance will be conducted under
AITD (e.g., maintaining a training fleet
separate from brigades, etc.)

Answer: 1. The AITD contractor will not
provide aircraft maintenance. 2. Buildup
refers to transition in.

Question: Please explain what buildup for
Airfield Operations and Support mission
entails at AITD.

Answer: None

Reference:

Text states that the Contractor will staff the
Training Management Office with certified
Training and Management Specialists.

Question: Please describe in more detail the
type and level of certification that the
Government desires to have in these
specialists.

Answer: Contractor is responsible to define
their personnel qualifications to meet the
PWS requirements

Reference:

Text states The contractor shall provide OJT to
MNG AVN personnel, currently 10 level certified,
in achieving 20 level certifications within 18
months; and provide OJT to MNG AVN personnel
with 20 level to 30 level certifications training
within 12 months.

Question: What is the current total number of
MNG AVN personnel in the OJT training
program by MOS directly related to the AITD
mission?

Answer: PMO will revise the PWS and post.

Reference:

Text states The contractor shall use the MNG
provided Maintenance Management System to
manage and document the overall maintenance
program and aircraft status for assigned aircraft.

Question: Are you asking the contractor to manage
and document the overall maintenance program even
though another contractor may possibly be performing
the work? And if the answer is yes, what guidelines will
the Government provide to facilitate possible interaction
with the other contractor?

Answer: The AITD contractor is not required
to conduct aircraft maintenance.

Reference:

Text states The contractor shall use the MNG
provided Logistics and Supply Chain Management
System to manage the overall re-order, order,
replenishment stock level, Supply class tracking,
and parts tracking program for the Supply Chain
Management System.

Question: Are you asking the contractor to manage
the program Supply Chain Management system even
though another contractor may possibly be performing
the work? And if the answer is yes, what guidelines will
the Government provide to facilitate possible interaction
with the other contractor?

Answer: No; Contractor shall input work order and
work requests into ERP system. MNG shall approve
and source via different government sourcing outside
of this contract.

Reference:

Text states Training, and Sustainment Support of
ULLS_A Electronic Logbook Database and Flight
Line Wireless Network for the Saudi Arabia
National Guard (MNG).

Question: Are you asking the contractor to maintain
ULLS-A and a Flightline Wireless System even though
another contractor may possibly be performing the
work? And if the answer is yes, what guidelines will
the Government provide to facilitate possible interaction
with the other contractor?

Answer: No.

Reference:

Text states, On-the-Job Training (OJT)
Program and in the following paragraphs
state Air Traffic Control and Crash Fire
Rescue.

Question: Are you asking the contractor to provide OJT
to ATC and ARFF personnel even though that work
aligns with another contractors scope of work? And if
the answer is yes, what guidelines will the Government
provide to facilitate possible interaction with the other
contractor?

Answer: No; the only requirement is to coordinate
with the other contractor the times for students to
receive OJT

Reference:

Text states, The contractor shall designate a
separate English Language (ELT) focused
Program Manager and that they shall
supervise and direct all ELT efforts in support
of MNG, to include English Language
Training Programs (ELTPs) at NGMS and
AVN Institute.

Question: Are you asking for additional ELT
courses and will they be taught at the same
location or at the NGMS?

Answer: The PWS will be revised to delete
NGMS.

Reference:

Text states, On the Job Training and the sub-
paragraphs refer to 16 aircraft maintenance specific
jobs for initial training and coordinate OJT.

Question: Are you asking the contractor to develop
additional POIs that align with these 16 paragraphs?
Are you asking the contractor to provide OJT to these
16 aviation maintenance specific jobs even though that
work aligns with another contractors scope of work?
And if the answer is yes, what MOS proficiency levels
OJT will the AITD contractor instruct (10, 20, 30)?

Answer: 1. Yes. 2. No

Reference:

Text states The contractor shall provide
initial maintainer training and coordinate OJT
in ALSE daily operations, accountability
actions, routine maintenance IAW ATP 3-
04.7.

Question: Are you asking the contractor to provide
ALSE OJT even though that work possibly aligns
with another contractors scope of work? And if the
answer is yes, what MOS proficiency levels OJT
will the AITD contractor instruct (10, 20, 30)?

Answer: No; the only requirement is to coordinate
with the other contractor the times for students to
receive OJT

Reference:

Text states Logistics and Supply Chain
Management (LCSM) OJT

Question: Are you asking the contractor to conduct
Logistics and Supply Chain Management OJT even
though another contractor may possibly be performing
the work? And if the answer is yes, what MOS
proficiency levels OJT will the AITD contractor instruct
(10, 20, 30)?

Answer: No; the only requirement is to coordinate
with the other contractor the times for students to
receive OJT

Reference:

Text states The contractor shall maintain
designated supply warehouses

Question: Are you asking the contractor to
maintain designated supply warehouses? If
yes, please provide the scope for this work; number
of warehouses, location, hours of operations, size,
Answer: No; PWS has been revised to remove this
requirement

Reference:

Text states Crash, Fire, and Rescue Services
Question: Are you asking the contractor to provide OJT
to ARFF personnel even though that work aligns with
another contractors scope of work? And if the answer is
yes, what MOS proficiency levels OJT will the AITD
contractor instruct (10, 20, 30)?

Answer: No; the only requirement is to coordinate
with the other contractor the times for students to
receive OJT

Reference:

Text states ATC Tower Services OJT

Question: Are you asking the contractor to provide
OJT to ATC personnel even though that work aligns
with another contractors scope of work? And if the
answer is yes, what MOS proficiency levels OJT
will the AITD contractor instruct (10, 20, 30)?

Answer: The PWS will be revised.

Reference:

Text states Fueling/Defueling Operations
Question: Are you asking the contractor to
provide OJT to Fuel/Defuel personnel even though
that work aligns with another contractors scope of
work? And if the answer is yes, what MOS
proficiency levels OJT will the AITD contractor
instruct (10, 20, 30)?

Answer: The PWS will be revised.

Reference:

Text states Vehicle/Ground Support
Equipment Support OJT

Question: Are you asking the contractor to provide
Vehicle/Ground Support Equipment services OJT to
personnel even though that work aligns with another
contractors scope of work? And if the answer is
yes, what MOS proficiency levels OJT will the
AITD contractor instruct (10, 20, 30)?

Answer: The PWS will be revised

Reference:

Text requires the service contractor to provide
PPE for each employee IAW OSHA Code 29.

Question: Although the PWS text directs
contractor issue of PPE to each employee, is it
possible that some employees should be exempt
from this issue due to the nature of their work?

Answer: Yes

Reference:

Text states that the service contractor will
provide in-country site managers for points of
contact.

Question: Our team may want a site manager and a
deputy at the AITD site. However, to be clear,
please confirm that the AITD PWS will be
accomplished at a single site (i.e., Dirab).

Answer: Contractor is responsible to define their
personnel qualifications meet the PWS
requirements

Reference:

Text states The contractor shall implement
and maintain a certified Quality Management
System (QMS) IAW AS 9110.

Question: What QMS do you want the contractor
to follow and if the response is AS 9110, please
provide the Governments rationale as to why
9110 is appropriate.

Answer: The PWS will be revised

Reference:

Text states that The incumbent Contractor
shall provide training and a definitive date for
transferring all efforts . . . to the incoming
contractor

Question: Please provide a list of topics that
the incumbent contractor may provide during
this transition.

Answer: The PWS will be revised to reflect
an outgoing transition plan

Reference:

Text refers in the base year CLIN item
number 0003 and in each successive
corresponding option item a UIH-60E
aircraft.

Question: Please provide information on the
UH-60E and if this is a typo, please provide
the correct aircraft nomenclature (which we
think should have been UH-60V).

Answer: Type - RFP will be revised

Reference:

Text states that all files will be compressed
into one file for submission. It later states
that each file shall have a Table of Contents,
Summary Section, and Narrative Section.

Question: As there is some confusion on
number of files to be submitted and if file
refers to the proposal volume, please confirm
that separate TOC,