Summary
This presentation is from an industry day event related to the A22 - SAW_Manteo - Oregon Inlet Hopper contract. The industry day took place on March 25, 2021, at 2:00 pm. The agenda included introductions, details about the contract type, scope, and timeline, as well as a section for questions and wrap-up. Specifics of the contract highlighted in the presentation included it being a rental contract, with an environmental window from August 1 to March 30, involving a hopper dredge for achieving a project depth of 14ft +2ft during a 30-day dredging event at locations such as Oregon Inlet Bar, Oregon Inlet West, and nearshore disposal area. The presentation also provided contact information for key personnel involved in the project, including Project Manager Brennan Dooley and Ros Shoemaker.