80JSC020xEVAPS - Industry Day Questions and Answers.pdf
Posted: May 22, 2020
• Type: .pdf
• Size: 0.05MB
Submit Questions to Government Officer Anonymously
Place your question(s) below. One of our analysts will anonymously submit the question(s) within 8 hours and provide any responses via email once received.
Question & Answer Assistant
Hello! Please let me know your question about this document. I will answer based on the related documents for this opportunity.
Some suggestions:
I'd like to anonymously submit a question to the procurement officer(s)
Loading
Overview
Related Opportunity
Related Agency
Summary
Industry Day Questions and Answers for the Exploration Extravehicular Production and Services Contract (XEVAPS) were recently addressed by NASA. The document covers various inquiries from potential contractors regarding the contract specifics. Questions ranged from small business set-asides for specific contract line items to data access and management responsibilities under the XEVAPS contract.
NASA emphasized the importance of open access to XEVA system data while seeking input from industry partners on collaborative data environment (CDE) implementation.
Additionally, the document clarified that an RFI related to the draft statement of work was released on a specified date, and responses were due by a certain deadline. It also touched upon topics such as technical baseline ownership, contractor roles within the contract structure, access to suit designs for vendors, and concerns regarding organizational conflicts of interest.
The document provided insights into the anticipated number of users for the CDE and sought feedback on various aspects like CAD file delivery formats and cloud hosting preferences for the system.
NASA emphasized the importance of open access to XEVA system data while seeking input from industry partners on collaborative data environment (CDE) implementation.
Additionally, the document clarified that an RFI related to the draft statement of work was released on a specified date, and responses were due by a certain deadline. It also touched upon topics such as technical baseline ownership, contractor roles within the contract structure, access to suit designs for vendors, and concerns regarding organizational conflicts of interest.
The document provided insights into the anticipated number of users for the CDE and sought feedback on various aspects like CAD file delivery formats and cloud hosting preferences for the system.