DOCUMENT

2022-08-15 AOC Phase 1 Industry Day DRAFT BID SCHEDULE.pdf

OVERVIEW

Original Source
Contract Opportunity
Posted
Aug. 18, 2022
Type
.pdf
Size
0.17MB

DOCUMENT PREVIEW

EXTRACTED TEXT

Atlantic Ocean Channel
Virginia Beach, VA

RFP NUMBER:
OFFEROR'S NAME:

CONTRACT LINE ITEM SCHEDULE - ATLANTIC OCEAN CHANNEL PHASE 1

Item No.

Description

Quantity

Amount

Line Item
Price

BASE BID

All costs connected with the mobilization and
demobilization, inclusive of additional
remobilizations and demobilizations for seasonal
restriction windows, of the Contractor's plant and
equipment for dredging Atlantic Ocean Channel
and overboard placement at the Dam Neck Ocean
Disposal Site (DNODS) are included in this bid
item.

Entire work with labor, material, equipment,
testing, transportation, and all appurtenances to
dredge Atlantic Ocean Channel to a depth of -59
feet with one foot of allowable overdepth. and
dispose of the material at Dam Neck Ocean
Disposal Site (DNODS), in accordance with the
plans and specifications. Final quantity shall be
adjusted up or down depending on the project
requirements and volume measurements. Post
dredging clean-up of shoals regardless of means
and methods (hydraulic or mechanical) shall be
paid for under this line item. Removal of material
accumulated due to accretion shall also be paid
under this line item.

Turtle trawling includes all
mobilization/demobilization time of the trawler
and all material, equipment, and labor required
to accomplish the intented in accordance with
Section 01 57 40 of the specifications for turtle
trawling details.

Live Sea Turtle Take and Rehabilitation 2023
Costs. Level 1: $1,335. Level 2: $13,849. Level 3:
$54,262. See Measurement and Payment section
01 22 00 of the specifications for more details.

TOTAL BASE BID

OPTION BID

2,424,700

LIVE TURTLE
$69,446
DRAFT - NOT FOR SOLICITATION1005

Atlantic Ocean Channel
Virginia Beach, VA

All costs connected with the mobilization and
demobilization (beyond CLIN 1001), inclusive of
additional remobilizations and demobilizations
for seasonal restriction windows, of the
Contractor's plant and equipment for the
placement of dredged material at Craney Island
Dredged Material Management Area (CIDMMA)
are included in this bid item. Mobilization shall
include all Contractor costs for operations
accomplished prior to CIDMMA dredged material
placement operations; this shall include site
preparation; transfer of attendant plant and
equipment to site; placement site inspection; and
any other associated work that is necessary in
advance of actual dredging operations.
Demobilization shall include demobilization of all
equipment, restoration of original site conditions,
and cleanup of the Contractor's staging area.

Containment Area Earthwork activities within the
CIDMMA. This item shall include construction of a
sub-containment area at the placement site as
indicated and specified to function as a protective
barrier to isolate the placed dredged material
from other onging operations within the
CIDMMA. Work at the borrow site included in
this bid item also includes maintenance of the
constructed sub-containment area during
placement operations, excavation and mixing of
materials, and transport of materials. All
methods, material and labor required to
construct this item in accordance with plans and
specifications shall be all inclusive and complete.

Payment to be made for this item includes all
additive unit costs beyond that included in CLIN
1002 above, associated with material dredged
from stations 1880+00 to 1942+00 with
placement at the CIDMMA, including additional
transport of the dredged material prior to pump
out, screening of material at the pipeline
discharge end, Ordnance and Expolsives Safety
Specialist work, and all other associated costs.

1,437,100

DRAFT - NOT FOR SOLICITATION1008

500,100

487,500

LIVE TURTLE
$69,446

Atlantic Ocean Channel
Virginia Beach, VA

Payment to be made for this item includes all
additive unit costs beyond that included in CLIN
1002 above, associated with material dredged
from stations 1942+00 to 1960+00 with
placement at the CIDMMA, including additional
transport of the dredged material prior to pump
out, screening of material at the pipeline
discharge end, Ordnance and Expolsives Safety
Specialist work, and all other associated costs.

Payment to be made for this item includes all
additive unit costs beyond that included in CLIN
1002 above, associated with material dredged
from stations 1960+00 to 1978+00 with
placement at the CIDMMA, including additional
transport of the dredged material prior to pump
out, screening of material at the pipeline
discharge end, Ordnance and Expolsives Safety
Specialist work, and all other associated costs.

Optional Live Sea Turtle Take and Rehabilitation
2023 Costs. Level 1: $1,335. Level 2: $13,849.
Level 3: $54,262. See Measurement and Payment
section 01 22 00 of the project specifications for
more details.

Optional Contracting Officer directed standby
time. The contract price per day for Contracting
Officer directed standby time shall include the
Contractor's costs for holding his plant,
equipment, and crew on site until further
direction is given by the Contracting Officer. Time
will be measured and paid for by the day (24
hours) and calculated to the nearest hour (1/24
day) for payment.

TOTAL OPTION BID
TOTAL BASE + OPTION BID

Hopper dredging.

Combination of hopper and mechanical dredging.
Mechanical dredging.

The Contractor must check one box below to indicate method of dredging to be used:
$
DRAFT - NOT FOR SOLICITATION