Anchor Windlass, Overhaul

UPDATED SOW 10/21/21 70Z080-22-Q-LEGARE25 CGC LEGARE

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect and refurbish the port anchor windlass. Period of performance for overhaul NOV 1 - Dec 17 2021. POC LT Andrew Bohuslav. PH 757-483-8750 CGC LEGARE returns to home port Oct 21, 2021.

1.2 Government-furnished property. X-1836 Overhaul Kit NSN: 4940-01-599-9029

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 905 WMEC 185-004, Rev E, Anchor Windlass Fdn

Coast Guard Drawing 905 WMEC 185-005, Rev -, Installation of Jered Anchor Windlass & Warping Capstan “B” Class MEP

Coast Guard Drawing 905 WMEC 581-001, Rev D, Anchor Handling A & D

Coast Guard Drawing 905 WMEC 581-004, Rev D, Anchor Windlass A & D

Coast Guard Publications

Coast Guard Technical Publication (TP) 2837, Manufacturer's Instruction Book, SWBS Group 581, Section A, Jul 2016, Capstan-Windlass Model X-1836

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2018, Overhaul AC Electrical Motors

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2018, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

Other References

ITEM DESCRIPTION

NSN/PN

ESTIMATED COST

**Main Shaft

NSN: 3040-01-662-6448

PN: JC-14097-1

1 ea.

5,828.22

**Wild Cat

NSN: 3950-01-662-6433

PN: JA-14082-1

1 ea.

43,651.63

**Capstan Head

NSN: 3950-01-662-6522

PN: JA-12634-3

1 ea.

42,449.22

**Shaft (STBD Windlass Only)

NSN:3040-01-662-6500

PN: JA-14787.18

1 ea.

1,211.19

**Shaft (Port Windlass Only)

NSN: 3040-01-662-0106

PN: JA-14787.22

1 ea.

1,211.19

**Sliding-Clutch Hub

NSN: 3040-01-662-1571

PN: JB-12982-1

1 ea.

6,390.15

**Spur Gear

NSN: 3020-01-662-0092

PN: JD-14060

1 ea.

7,409.28

**Brake Drum

NSN: 3040-01-662-1592

PN: JB-14089-00

1 ea.

13,165.08

**Gear, Helical

NSN: 3020-01-662-3019

PN: JD-14058

1 ea.

4,701.21

**Bevel Gear, Hardened Teeth

NSN: 3020-01-662-3391

PN: JA-14087-14

1 ea.

2,167.74

**Motor 20/15HP

NSN: 6105-01-662-3403

1 ea.

23,769.63

X-1836 Overhaul Kit

NSN: 4940-01-599-9029

PN: J199532

1 kt.

10,907.64

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:

3.2 Work particulars, Task 1

3.2 Work particulars, Task 4

3.2 Work particulars, Task 5

3.2 Work particulars, Task 6

3.2 Work particulars, Task 7

3.2 Work particulars, Task 8

3.2 Work particulars, Task 9

3.2 Work particulars, Task 10

3.2 Work particulars, Task 11

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

The windlass assembly may be mounted on a bed of chockfast; without a releasing agent, significant effort will be required to remove mounting bolts and break foundation plate from the chockfast material. Chockfast must be renewed, in accordance with manufacturer’s recommendation, upon windlass reinstallation.

3.2 Work particulars. The Contractor shall perform the work described herein in accordance with SFLC Std Spec 5000 (see paragraph 4.1 (Paragraph number relationships)), SFLC Std Spec 3020, TP 2837, and using Coast Guard Drawings 905 WMEC 581-001 and 905 WMEC 581-004 as guidance.

Table 1 - Additional Requirements

TASK TYPE

COMPONENT OR ASSEMBLY

APPENDIX PARA. FROM SFLC STD SPEC 5000

OTHER

Operate and Inspect

Anchor Windlass and Capstan Assembly

3.2.1 (Operate and Inspect)

Accomplish prior to repairs. Submit CIR. See paragraph 3.1.1 in Std Spec 5000.

OP and Weight Test

Anchor Windlass and Capstan Assembly

3.2.8 (Operational and weight testing)

B2.5 (Anchor windlass)

Accomplish after repairs.

See paragraph 3.1.11 in Std Spec 5000.

The following tests are required:

Static Load Test (Conditional; see 3.3.1)

No Load Test (see 3.3.2)

Rated Load Test (see 3.3.3): 10,000 lbs @ 40 fpm

Torsion Test, Electric Brake (see 3.3.4):

15,000 lbs

Band Brake Test (see 3.3.5):

15,000 lbs

Wildcat Operational Test (B2.5.2 of Std Spec 5000)

Submit CFR. See paragraph 3.1.1 in Std Spec 5000.

If pier restrictions prohibit testing IAW Std Spec 5000, Contractor shall submit a CFR for an alternative method of proof testing.

Fabricate and Install

Label plate

B2.9 (Label plates)

System: Anchor Windlass

Disassemble and Inspect; Preserve

Main Reduction Gear Box

D2.4 (Open gearing and gear reducers)

Submit A CIR.

Disassemble and Inspect; Preserve

Main shaft assembly

3.2.3 (Disassemble and inspect)

3.2.4 (Preservation)

Submit A CIR.

Overhaul; Preserve

Electric Motor Assembly and Motor Reducer

Perform per SFLC Std Spec 3020

Submit A CIR.

Disassemble and Inspect

Disc Brake Assembly

D2.3 (Brakes and clutches)

Submit A CIR.

Disassemble and Inspect

Band Brake Assembly

D2.3 (Brakes and clutches)

Submit A CIR.

Disassemble and Inspect; Preserve

Band Brake Hand-Wheel, Bevel Gear Stand, and Linkage Assembly

3.2.3 (Disassemble and inspect)

3.2.4 (Preservation)

Submit A CIR.

Disassemble and Inspect; Preserve

Axial Dog Clutch Mechanism

3.2.3 (Disassemble and inspect)

3.2.4 (Preservation)

Submit A CIR.

Disassemble and Inspect; Preserve

Local Windlass and Capstan Controller –Applicable to 270 WMEC

3.2.3 (Disassemble and inspect)

3.2.4 (Preservation)

Submit A CIR.

Renew

Bearings and Gaskets/Seals

All parts in X-1836 Overhaul Kit shall be installed.

Renew

Chock-Fast/sealant for windlass assembly and bevel gear stand.

Install in accordance with manufacturer’s instructions.

Renew

100% of fasteners that attach each windlass assembly to the deck

D2.1 (Fastener assemblies)

Torque fasteners using TP 2837 as guidance.

Preserve; NDE

Anchor Windlass Foundation

SFLC Std Spec 6310, Appendix A, “Machinery, Deck” Option IV

Finish coat color: Select to match surrounding surfaces.

Weld joints to NDE: All foundation welds.

Groom and Lubricate

Anchor Windlass Assembly

3.2.6 (Groom and lubricate)

Lubricate Anchor Windlass assembly using TP 2837 as guidance.

3.3 Operational and Weight Test. When referred to in Table above, the Contractor shall accomplish the following procedures for testing. If the Cutter’s deck fittings will be used in the rigging of test weights, ensure that Work Item “Towing Bitts, Chocks, and Fairleads; Inspect and Test” is accomplished prior to rigging test weights.

3.3.1 Static Load Test. If a Change Request has been approved for repair or modification of structural members, the anchor windlass assembly shall be subjected to a static test by placing a loop of line over the capstan head at midheight and 90 degrees to its axis to produce bending moment only. Using the capstan head as a bitt, a load of 64,200 lbs shall be applied and held for a minimum of 10 minutes. Do not operate Anchor Windlass during this test, and do not use the Anchor Windlass to rig test weight into place. Remove the test weight. Verify no permanent deformation or damage to any components.

3.3.2 No Load Test. The anchor windlass assembly shall be run without load at each rated speed for five minutes in each direction to determine that no abnormal heat, wear or noise develops. Note, when brake repair has been accomplished an inspection of brake assembly is to be accomplished after no load test to ensure proper installation.

3.3.3 Rated Load Test. The capstan head of the anchor windlass assembly shall be capable of developing the specified line pull and speed in both directions of rotation. The capstan shall be run at rated load(s) and rated speed(s) for a period of one half hour in each direction. Approved methods of testing include; line and weight, static line arrangement and prony brake (dynamometer). See Figures 1 and 2 for suggested test arrangement.

3.3.4 Torsion Test, Electric Brake. This test is for the electric disk brake. With the band brake set and wildcat disengaged, and with the capstan head rigged as for developing normal line pull ea… Show All