W912HY21C0021
Definitive Contract
Overview
Government Description
HOUSTON SHIP CHANNEL GREENS BAYOU TO SIMS BAYOU, GREENS BAYOU CHANNEL, PIPELINE DREDGING, HARRIS COUNTY, TEXAS. SCHEDULE 1 AND OPTION 2
Awardee
Awarding Agency
Funding Agency
Place of Performance
Houston, TX 77015 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 11/02/22 to 02/15/23.
Recompete The following similar solicitation(s) may continue aspects of this contract: HOUSTON SHIP CHANNEL ROSA ALLEN PA IMPROVEMENTS, HARRIS COUNTY, TEXAS
Unrealized Backlog This Definitive Contract is complete with $1,920,000 of unfunded backlog unused.
Recompete The following similar solicitation(s) may continue aspects of this contract: HOUSTON SHIP CHANNEL ROSA ALLEN PA IMPROVEMENTS, HARRIS COUNTY, TEXAS
Unrealized Backlog This Definitive Contract is complete with $1,920,000 of unfunded backlog unused.
Matthews Brothers Dredging was awarded
Definitive Contract W912HY21C0021 (W912HY-21-C-0021)
worth up to $17,515,149
by the U.S. Army Corps of Engineers
in September 2021.
The contract
has a duration of 1 year 5 months and
was awarded
through solicitation FY 21 Pipeline Dredging Deep Draft Houston Ship Channel - Greens Bayou to Sims Bayou Harris, County, Texas
full & open
with
NAICS 237990 and
PSC Z1KF
via sealed bid acquisition procedures with 3 bids received.
As of today, the Definitive Contract has a total reported backlog of $1,920,000, though the contract is complete, so backlog may not be realized.
Status
(Complete)
Last Modified 4/11/23
Period of Performance
9/27/21
Start Date
2/15/23
Current End Date
2/15/23
Potential End Date
Obligations and Backlog
$15.6M
Total Obligated
$15.6M
Current Award
$17.5M
Potential Award
$0.0
Funded Backlog
$1.9M
Total Backlog
Award Hierarchy
Definitive Contract
W912HY21C0021
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W912HY21C0021
Transaction History
Modifications to W912HY21C0021
People
Suggested agency contacts for W912HY21C0021
Competition
Number of Bidders
3
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
XMMAJTXHRHC5
Awardee CAGE
47YG2
Agency Detail
Awarding Office
W912HY US ARMY ENGINEER DISTRICT GALVESTON
Funding Office
None
Created By
traci.d.robicheaux@usace.army.mil
Last Modified By
traci.d.robicheaux@usace.army.mil
Approved By
traci.d.robicheaux@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
TX-29
Senators
John Cornyn
Ted Cruz
Ted Cruz
Representative
Sylvia Garcia
Budget Funding
| Federal Account | Budget Subfunction | Object Class | Total | Percentage |
|---|---|---|---|---|
| Operation and Maintenance, Corps of Engineers-Civil (096-3123) | Water resources | Land and structures (32.0) | $8,680,608 | 100% |
Modified: 4/11/23