Search Prime Contracts

W912HN25C5007

Definitive Contract

Overview

Government Description
Noyes cut phase 2 - USACE - savannah district. The contractor will close one man-made cut in the salt marsh north of the satilla river in camden county, GA, as part of the noyes cut ecosystem restoration project, with the objective of increasing tidal exchange throughout the system, restoring salinity gradients to dover creek, and reducing shoaling in umbrella creek. Includes constructing a trapezoidal rubble mound-type structure approximately 495 feet long using gdot type I riprap, furnishing, stockpiling, and placing about 21,000 tons of rock, and installing AIDS to navigation at the closure location. All work will be conducted from floating platforms to minimize impacts to the marsh and wildlife, and any marsh damaged outside the established footprint will be restored by the contractor.
Place of Performance
Kings Bay, GA 31547 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 10/09/26 to 10/27/26.
Russell Marine was awarded Definitive Contract W912HN25C5007 (W912HN-25-C-5007) for Noyes Cut Phase 2 - USACE - Savannah District worth up to $5,273,000 by the U.S. Army Corps of Engineers in October 2026. The contract was awarded through solicitation Noyes Cut Ecosystem Restoration Phase Two full & open with NAICS 237990 and PSC Y1PZ via sealed bid acquisition procedures with 7 bids received.

Status
(Open)

Last Modified 10/27/25
Period of Performance
10/9/26
Start Date
10/27/26
Current End Date
10/27/26
Potential End Date
0% Complete

Obligations
$5.3M
Total Obligated
$5.3M
Current Award
$5.3M
Potential Award
100% Funded

Award Hierarchy

Definitive Contract

W912HN25C5007

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to W912HN25C5007

Opportunity Lifecycle

Procurement history for W912HN25C5007

Transaction History

Modifications to W912HN25C5007

People

Suggested agency contacts for W912HN25C5007

Competition

Number of Bidders
7
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
EGMVLKWT42N1
Awardee CAGE
60E56
Agency Detail
Awarding Office
W912HN W074 ENDIST SAVANNAH
Funding Office
960102
Created By
glenda.a.canty@usace.army.mil
Last Modified By
glenda.a.canty@usace.army.mil
Approved By
glenda.a.canty@usace.army.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements Labor Standards
Performance District
GA-01
Senators
Jon Ossoff
Raphael Warnock
Representative
Earl Carter
Modified: 10/27/25