W912HN23C3002
Definitive Contract
Overview
Government Description
ABMS FACILITY HANGAR
Awardee
Awarding / Funding Agency
Place of Performance
Warner Robins, GA 31098 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 01/16/26 to 03/29/26 and the Potential Award value has increased 3% from $99,852,450 to $102,901,534.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
ACC Construction Co was awarded
Definitive Contract W912HN23C3002 (W912HN-23-C-3002)
for Abms Facility Hangar
worth up to $102,901,534
by USACE Savannah District
in February 2023.
The contract
has a duration of 3 years 1 months and
was awarded
through solicitation ABMS FoS Maintenance and Logistics Facility Robins AFB, GA
full & open
with
NAICS 236220 and
PSC Y1BZ
via sealed bid acquisition procedures with 3 bids received.
As of today, the Definitive Contract has a total reported backlog of $1,270,291.
DOD Announcements
Jan 2023:
ACC Construction Co. Inc., Augusta, Georgia, was awarded a $99,612,848 firm-fixed-price contract to construct an Advanced Battle Management System family of systems hangar complex. Bids were solicited via the internet with three received. Work will be performed at Robins Air Force Base, Georgia, with an estimated completion date of Jan. 27, 2026. Fiscal 2023 other procurement, Air Force funds in the amount of $39,525,413 were obligated at the time of the award. U.S. Army Corps of Engineers, Savannah, Georgia, is the contracting activity (W912HN-23-C-3002).
Status
(Open)
Last Modified 2/11/25
Period of Performance
2/1/23
Start Date
3/29/26
Current End Date
3/29/26
Potential End Date
Obligations and Backlog
$101.6M
Total Obligated
$101.6M
Current Award
$102.9M
Potential Award
$0.0
Funded Backlog
$1.3M
Total Backlog
Award Hierarchy
Definitive Contract
W912HN23C3002
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W912HN23C3002
Transaction History
Modifications to W912HN23C3002
People
Suggested agency contacts for W912HN23C3002
Competition
Number of Bidders
3
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Performance Based Acquisition
Yes
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
QXNSEJFDC1K3
Awardee CAGE
0FZ73
Agency Detail
Awarding Office
W912HN W074 ENDIST SAVANNAH
Funding Office
W33SJG
Created By
brian.m.murray@usace.army.mil
Last Modified By
brian.m.murray@usace.army.mil
Approved By
brian.m.murray@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
GA-02
Senators
Jon Ossoff
Raphael Warnock
Raphael Warnock
Representative
Sanford Bishop
Modified: 2/11/25