SAN JUAN HARBOR CONSTRUCTION AND MAINTENANCE DREDGING 44-FOOT AND 36-FOOT PROJECT, SAN JUAN, PUERTO RICO
Place of Performance
San Juan, PR 907 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Infrastructure $34,453,240 (63%) percent this Definitive Contract was funded by the 2021 Infrastructure Act.
Amendment Since initial award the Potential End Date has been extended from 07/31/24 to 11/26/24 and the Potential Award value has increased 1% from $56,700,015 to $57,501,079.
Unrealized Backlog This Definitive Contract is complete with $2,501,529 of unfunded backlog unused.
Curtin Maritime was awarded Definitive Contract W912EP23C0017 (W912EP-23-C-0017) for San Juan Harbor Construction And Maintenance Dredging 44-Foot And 36-Foot Project, San Juan, Puerto Rico worth up to $57,501,079 by USACE Jacksonville District in July 2023. The contract has a duration of 1 year 4 months and was awarded through solicitation San Juan Harbor Construction and Maintenance Dredging, 44-Foot and 36-Foot Project, San Juan, Puerto Rico full & open with NAICS 237990 and PSC Z1KF via sealed bid acquisition procedures with 7 bids received. As of today, the Definitive Contract has a total reported backlog of $2,501,529, though the contract is complete, so backlog may not be realized.

DOD Announcements

Jun 2023: Curtin Maritime Corp.,* Long Beach, California, was awarded a $54,204,676 firm-fixed-price contract for San Juan Harbor construction and maintenance dredging. Bids were solicited via the internet with seven received. Work will be performed in San Juan, Puerto Rico, with an estimated completion date of July 31, 2024. Fiscal 2023 civil construction funds in the amount of $54,204,676 were obligated at the time of the award. U.S. Army Corps of Engineers, Jacksonville, Florida, is the contracting activity (W912EP-23-C-0017).

Status
(Complete)

Last Modified 10/18/24
Period of Performance
7/7/23
Start Date
11/26/24
Current End Date
11/26/24
Potential End Date
100% Complete

Obligations and Backlog
$55.0M
Total Obligated
$55.0M
Current Award
$57.5M
Potential Award
96% Funded
$0.0
Funded Backlog
$2.5M
Total Backlog

Award Hierarchy

Definitive Contract

W912EP23C0017

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to W912EP23C0017

Opportunity Lifecycle

Procurement history for W912EP23C0017

Transaction History

Modifications to W912EP23C0017

People

Suggested agency contacts for W912EP23C0017

Competition

Number of Bidders
7
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
CMCFMRN32267
Awardee CAGE
4ADU6
Agency Detail
Awarding Office
W51DQV W2SR ENDIST CARIBBEAN(PROVIS)
Funding Office
964224
Created By
carlos.r.lugoramos.w51dqv@usace.army.mil
Last Modified By
carlos.r.lugoramos.w51dqv@usace.army.mil
Approved By
carlos.r.lugoramos.w51dqv@usace.army.mil

Legislative

Legislative Mandates
None Applicable
Performance District
PR-98

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Construction, Corps of Engineers - Civil (096-3122) Water resources Land and structures (32.0) $36,273,854 67%
Rivers and Harbors Contributed and Advance Funds, Corps of Engineers, Civil (096-8862) Water resources Land and structures (32.0) $9,470,123 17%
Operation and Maintenance, Corps of Engineers-Civil (096-3123) Water resources Land and structures (32.0) $8,460,700 16%
Modified: 10/18/24