Project requires demolition of the tenkiller bridge in sequoyah county, design and construction of temporary electrical and safety walkways, construction of a new bridge, new electrical/catwalks/water lines, and full site restoration. Includes demolition of existing bridge components such as pedestals, girders, beams, deck, sidewalks, guardrails, electrical power/lighting systems, utilities, catwalks, and appurtenances as indicated on the drawings. Tasks also include design and construction of temporary electrical service for uninterrupted operation of government facilities, construction of safety walkways for access to tainter gate controls and power systems in accordance with OSHA and em 385-1-1, and construction of a new bridge with precast components using Ultra High-Performance Concrete (UHPC), new electrical power/lighting systems, new catwalks and supporting systems, installation of new water lines under the bridge, and restoration of the site to preconstruction conditions.
Awardee
Awarding Agency
Funding Agency
Place of Performance
Vian, OK 74962 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Kiewit Infrastructure South Co was awarded
Definitive Contract W912BV25C0012 (W912BV-25-C-0012)
for Tenkiller Dam Spillway Bridge Replacement (UHPC, OSHA, USACE)
worth up to $28,695,642
by the U.S. Army Corps of Engineers
in June 2025.
The contract
has a duration of 1 year 7 months and
was awarded
through solicitation Tenkiller Spillway Bridge Replacement
full & open
with
NAICS 237310 and
PSC Y1LB
via direct negotiation acquisition procedures with 3 bids received.
DOD Announcements
May 2025:
Kiewit Infrastructure South Co., Westlake, Texas, was awarded a $28,695,642 firm-fixed-price contract for demolition and construction of bridge systems. Bids were solicited via the internet with three received. Work will be performed in Gore, Oklahoma, with an estimated completion date of Feb. 20, 2026. Fiscal 2025 civil construction funds in the amount of $28,695,642 were obligated at the time of the award. U.S. Army Corps of Engineers, Tulsa, Oklahoma, is the contracting activity (W912BV-25-C-0012).
Status
(Open)
Last Modified 11/4/25
Period of Performance
6/2/25
Start Date
1/22/27
Current End Date
1/22/27
Potential End Date
Obligations
$28.7M
Total Obligated
$28.7M
Current Award
$28.7M
Potential Award
Award Hierarchy
Definitive Contract
W912BV25C0012
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W912BV25C0012
People
Suggested agency contacts for W912BV25C0012
Competition
Number of Bidders
3
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Yes
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
RK7NKN684PC3
Awardee CAGE
1F7W9
Agency Detail
Awarding Office
W912BV W076 ENDIST TULSA
Funding Office
967273
Created By
miguel.a.martinez2@usace.army.mil
Last Modified By
jeremie.evans.w912bv@sa2100.army.mil
Approved By
dario.m.rissone@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
OK-02
Senators
James Lankford
Markwayne Mullin
Markwayne Mullin
Representative
Josh Brecheen