Overview

Government Description
Design-bid-build construction services. Includes constructing a new single-story, 5,000 square-foot headquarters (HQ) building with metal-stud construction featuring management offices, open cubicle work areas, conference room, information center, communication, mechanical and electrical rooms, restrooms, nursing room, kitchen, storage room, and copy room, as well as a new single-story, 4,200 square-foot maintenance shop with a storage mezzanine, maintenance bays, management office, open cubicle work areas, electrical room, restroom, locker room, kitchen, tool room, and storage mezzanine at H.L. Englebright dam and lake in smartsville, CA. The project includes demolition and removal of two existing buildings and three shed structures, construction of new pre-engineered metal buildings for equipment and hazardous material sheds, grading, utilities installation, oxidation pond relining, asphaltic concrete paving, sidewalks, curbs, fencing, and landscaping.
Awardee
Place of Performance
Smartsville, CA 95977 United States
Pricing
Fixed Price
Set Aside
Small Business Set Aside - Total (SBA)
Extent Competed
Full And Open Competition After Exclusion Of Sources
Analysis Notes
Amendment Since initial award the Potential End Date has been shortened from 05/02/28 to 05/01/28.
R2build was awarded Definitive Contract W9123826CA004 (W91238-26-C-A004) for Design-Bid-Build Construction Services Englebright Dam Headquarters worth up to $18,935,765 by USACE Sacramento District in May 2026. The contract has a duration of 2 years and was awarded through solicitation USACE SPK DBB Construction - Englebright Dam and Lake HQ Building and Maintenance Shop ?Smartsville, California. with a Small Business Total set aside with NAICS 236220 and PSC Y1JZ via sealed bid acquisition procedures with 3 bids received.

DOD Announcements

Apr 2026: R2BUILD,* Irvine, California, was awarded a firm-fixed-price contract for construction of a new single-story 5,000-square-foot headquarters building and a new single-story 4,200-square-foot maintenance shop with storage mezzanine at the Englebright Dam and Lake Maintenance Shop in Smartsville, California. The amount of this action is $18,935,765. Bids were solicited via the internet with three received. Work will be performed in Smartsville, California, with an estimated completion date of March 30, 2028. Fiscal 2026 construction, Corps of Engineers, Civil funds in the amount of $18,935,765 were obligated at the time of the award. U.S. Army Corps of Engineers, Sacramento District, is the contracting activity (W91238-26-C-A004).

Status
(Open)

Last Modified 7/13/26
Period of Performance
5/13/26
Start Date
5/1/28
Current End Date
5/1/28
Potential End Date
21.0% Complete

Obligations
$18.9M
Total Obligated
$18.9M
Current Award
$18.9M
Potential Award
100% Funded

Award Hierarchy

Definitive Contract

W9123826CA004

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to W9123826CA004

Opportunity Lifecycle

Procurement history for W9123826CA004

Transaction History

Modifications to W9123826CA004

People

Suggested agency contacts for W9123826CA004

Competition

Number of Bidders
3
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
QH43GMN2LVK7
Awardee CAGE
7NLY2
Agency Detail
Awarding Office
W91238 W075 ENDIST SACRAMENTO
Funding Office
W62N6M
Created By
rachel.kinney@acws
Last Modified By
marie.a.jerman.civ.w91238@sa2100
Approved By
rachel.kinney@acws

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
CA-03
Senators
Dianne Feinstein
Alejandro Padilla
Representative
Kevin Kiley
Modified: 7/13/26