Hill Air Force Base building 225 area D roof replacement and office space renovation. Includes removing and replacing the roof of area D of building 225 (B225) at Hill Air Force Base (HAFB) in Utah, as well as renovating office space in B225. Tasks involve all civil, architectural, geotechnical, structural, utilities, landscaping, security, mechanical, electrical, demolition, and communications work, including demolition and reconstruction of existing office space along the north-south direction in the middle of aircraft maintenance hangar building 225 area D. Additional work includes seismic upgrades, skylight removal, conversion of a hobby shop to a machine shop, relocation of a 4160V beacon electrical line, installation of compressed air tanks and air drops, temporary walls, east egress tunnel construction, additional mechanical scope, and fall protection improvements.
Awardee
Awarding / Funding Agency
Place of Performance
Hill Afb, UT 84056 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 08/10/25 to 07/07/26 and the Potential Award value has increased 8% from $73,581,118 to $79,231,111.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
HHI Corporation was awarded
Definitive Contract W9123823C0021 (W91238-23-C-0021)
for HILL AFB Bldg 225 Roof Replacement & Office Renovation
worth up to $79,231,111
by USACE Sacramento District
in August 2023.
The contract
has a duration of 3 years and
was awarded
through solicitation Hill AFB Building 225 Area D Renovation
full & open
with
NAICS 236220 and
PSC Z2BZ
via two step acquisition procedures with 1 bid received.
DOD Announcements
Jul 2023:
HHI Corp., Ogden, Utah, was awarded a $73,581,115 firm-fixed-price contract for roof repairs. Bids were solicited via the internet with one received. Work will be performed in Layton, Utah, with an estimated completion date of July 27, 2025. Fiscal 2010 military construction, Army funds in the amount of $73,581,115 were obligated at the time of the award. U.S. Army Corps of Engineers, Sacramento, California, is the contracting activity (W91238-23-C-0021).
Status
(Open)
Last Modified 5/15/26
Period of Performance
8/11/23
Start Date
7/7/26
Current End Date
7/7/26
Potential End Date
Obligations
$79.2M
Total Obligated
$79.2M
Current Award
$79.2M
Potential Award
Award Hierarchy
Definitive Contract
W9123823C0021
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W9123823C0021
Transaction History
Modifications to W9123823C0021
People
Suggested agency contacts for W9123823C0021
Competition
Number of Bidders
1
Solicitation Procedures
Two Step
Evaluated Preference
None
Performance Based Acquisition
Yes
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
MKM2UNBJVD95
Awardee CAGE
0DRY5
Agency Detail
Awarding Office
W91238 W075 ENDIST SACRAMENTO
Funding Office
W62N6M
Created By
michelle.a.spence@usace.army.mil
Last Modified By
fpdsadmin
Approved By
michelle.a.spence@usace.army.mil
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
UT-01
Senators
Mike Lee
Mitt Romney
Mitt Romney
Representative
Blake Moore
Modified: 5/15/26